Permit to Load & Permit to Strike Templates

Free, editable permit to load and permit to strike forms with the checks a Temporary Works Supervisor and Coordinator should complete before loading or removing temporary works.

Free to download, no sign up. White labelled so you can add your own company name and logo.

Need help using it?0151 332 6581info@matthewsroberts.com

Preview of the Permit to load and strike templates

About this template

What the Permit to load and strike templates is for

Permits to load and strike are the hold points that stop temporary works being used before they are ready, or removed before the permanent works can carry the load.

These two forms give your team a consistent record of the checks made and who authorised each step.

What is included

  • Permit to load with seven pre load checks
  • Permit to strike or dismantle with five pre strike checks
  • Links to the register reference and design revision
  • Sign off for the Temporary Works Supervisor and Coordinator

How to use it

Using the Permit to load and strike templates on your project

  1. 01

    Inspect against the design

    Check the installed works match the checked design and the ground is as assumed.

  2. 02

    Issue the permit to load

    Sign only when every check is complete and recorded.

  3. 03

    Confirm the permanent works

    Before striking, confirm the permanent works have reached the strength or stage the design requires.

  4. 04

    Issue the permit to strike

    Brief the striking sequence and exclusion zones, then sign.

Avoid these

Common mistakes we see on site

  • Loading before the design check certificate is received
  • Striking on age alone without confirming strength
  • Permits not linked to the register reference
  • Verbal approvals with no written record

Prefer us to handle it?

We can run this for you on site

Matthews & Roberts provides the people behind these templates: Temporary Works Coordinators, quantity surveyors, project managers and health and safety consultants across Liverpool, Manchester, the North West and North Wales.

Send us a message
Insights
View all insights

FAQ

Permit to Load & Permit to Strike Templates: questions

Who signs a permit to load?

Normally the Temporary Works Supervisor after inspection, with the Temporary Works Coordinator authorising it under the contractor's procedure.

What is a permit to strike?

A written authorisation to remove or dismantle temporary works once the permanent works can safely carry the loads.

Do these templates follow BS 5975?

They reflect the hold points BS 5975 describes. Always align them with your own company temporary works procedure.

Talk to us

Need support on your project?

Tell us about your site and what you need. We will come back within one working day with a clear proposal and a named consultant.

Call 0151 332 6581

Email info@matthewsroberts.com

3a Bridgwater Street, Baltic Triangle, Liverpool L1 0AR

Send us a message

Or call 0151 332 6581 or email info@matthewsroberts.com

We use your details only to reply to your enquiry.