Permit to Load and Permit to Strike Explained
Most temporary works incidents happen when items are first loaded or removed. Here is how permits to load and strike control both moments.
Read insightFree template · Temporary works
Free, editable permit to load and permit to strike forms with the checks a Temporary Works Supervisor and Coordinator should complete before loading or removing temporary works.
Free to download, no sign up. White labelled so you can add your own company name and logo.
Need help using it?0151 332 6581info@matthewsroberts.com

About this template
Permits to load and strike are the hold points that stop temporary works being used before they are ready, or removed before the permanent works can carry the load.
These two forms give your team a consistent record of the checks made and who authorised each step.
What is included
Temporary works
Temporary works procedures link together. These guides and templates cover the rest of the process.
Guides
Free templates
Where we have delivered this
Prefer us to run it for you? Temporary Works
How to use it
Check the installed works match the checked design and the ground is as assumed.
Sign only when every check is complete and recorded.
Before striking, confirm the permanent works have reached the strength or stage the design requires.
Brief the striking sequence and exclusion zones, then sign.
Avoid these
Prefer us to handle it?
Matthews & Roberts provides the people behind these templates: Temporary Works Coordinators, quantity surveyors, project managers and health and safety consultants across Liverpool, Manchester, the North West and North Wales.
Send us a messageRelated services
Most temporary works incidents happen when items are first loaded or removed. Here is how permits to load and strike control both moments.
Read insightTemporary works are far more common than many contractors realise. Here are the most common examples and why each one needs managing.
Read insightResponsibility for temporary works is shared across several roles. Here is who does what under CDM 2015 and BS 5975, including on multi contractor sites.
Read insightFree resources
FAQ
Normally the Temporary Works Supervisor after inspection, with the Temporary Works Coordinator authorising it under the contractor's procedure.
A written authorisation to remove or dismantle temporary works once the permanent works can safely carry the loads.
They reflect the hold points BS 5975 describes. Always align them with your own company temporary works procedure.