Under the NEC4 Engineering and Construction Contract the programme is central. Clause 31 sets out what the programme must show and clause 32 requires it to be revised at the intervals the contract states. The Project Manager accepts a submitted programme or gives reasons for not accepting it within two weeks. The Accepted Programme is then used to assess the time effect of compensation events.
On JCT projects we support programme development, progress monitoring and the records needed to show the programme effect of relevant events, working alongside your commercial and project teams.
In both cases we help keep submissions, updates, milestones, change and contemporaneous records in order. Contractual entitlement remains a matter for your commercial or legal advisers.