Responsibility for temporary works is shared, but the Principal Contractor has overall responsibility for coordinating them across the site. Each contractor remains responsible for its own temporary works, managed through a procedure that follows BS 5975.
The legal duties
CDM 2015 requires structures to be kept stable during construction and excavations to be made safe. It places duties on the client, designers, the Principal Contractor and every contractor. Temporary works are part of the construction phase the Principal Contractor must plan, manage and monitor.
The BS 5975 roles
| Role | Responsibility |
|---|---|
| Designated Individual | Sets up the organisation's procedure and appoints competent TWCs |
| Temporary Works Coordinator | Manages the procedure on the project. See what a TWC does. |
| Temporary Works Supervisor | Controls installation, use and removal at the workface |
| Temporary works designer | Designs the item to the brief |
| Design checker | Checks the design to the agreed category |
| Principal Temporary Works Coordinator | Coordinates procedures across contractors on multi contractor sites |
Designated Individual
- Responsibility
- Sets up the organisation's procedure and appoints competent TWCs
Temporary Works Coordinator
- Responsibility
- Manages the procedure on the project. See what a TWC does.
Temporary Works Supervisor
- Responsibility
- Controls installation, use and removal at the workface
Temporary works designer
- Responsibility
- Designs the item to the brief
Design checker
- Responsibility
- Checks the design to the agreed category
Principal Temporary Works Coordinator
- Responsibility
- Coordinates procedures across contractors on multi contractor sites
Multi contractor sites
Where several contractors have their own temporary works, the Principal Contractor should make sure their procedures fit together and that interfaces are managed. BS 5975 recommends a Principal Temporary Works Coordinator for this.
The single document
The temporary works procedure sets out how temporary works will be managed on the project. It is supported by the temporary works register and referenced in the Construction Phase Plan.
The client's role
Clients must make sure suitable arrangements are in place, including enough time and resources. On complex projects many clients ask for evidence of the temporary works procedure at tender.
Support across the North West
Matthews & Roberts provides Temporary Works Coordinators and temporary works audits for contractors in Liverpool, Manchester, Chester, Warrington and across the North West. See also Principal Contractor support.
Frequently asked questions
Who has overall responsibility for temporary works on a multi contractor site?
The Principal Contractor plans, manages and coordinates the construction phase, including temporary works across all contractors. BS 5975 recommends a Principal Temporary Works Coordinator to coordinate the procedures of each contractor.
What is a Designated Individual?
A senior person in an organisation who is responsible for establishing and maintaining its temporary works procedure and for appointing competent Temporary Works Coordinators.
What single document sets out how temporary works will be managed?
The temporary works procedure, usually supported by the temporary works register and referenced in the Construction Phase Plan.
Temporary works
Related guides and templates
Temporary works procedures link together. These guides and templates cover the rest of the process.
Guides
- BS 5975 Explained: The Contractor's Guide to Temporary Works ProceduresThe code of practice behind every temporary works procedure.
- Temporary Works Coordinator Appointment Checklist for ContractorsWhat to confirm before you appoint a TWC.
- What Does a Temporary Works Coordinator Do?The TWC role day to day.
- Temporary Works Coordinator vs Temporary Works Supervisor: What Is the Difference?How the TWC and TWS roles divide the work.
Free templates
- Temporary Works Register TemplateExcel register with categories, checks and permits.Free · Excel and PDF
- Temporary Works Coordinator Appointment ChecklistCompetence, appointment and systems checks for a TWC.Free · Word and PDF
- Permit to Load & Permit to Strike TemplatesPermit forms ready to issue on site.Free · Word and PDF
Need support with temporary works on your project?