Free template · Contracts

JCT Extension of Time Notice Template

A free Word template for a contractor's notice of delay under a JCT contract, structured around the material circumstances, the cause, the expected effects and the estimated delay.

Free to download, no sign up. White labelled so you can add your own company name and logo.

Need help using it?0151 332 6581info@matthewsroberts.com

Preview of the JCT extension of time notice template

About this template

What the JCT extension of time notice template is for

Under JCT contracts the contractor must give written notice when it becomes reasonably apparent that progress is being or is likely to be delayed. In the Design and Build Contract that is clause 2.24. In the Standard Building Contract it is clause 2.27.

A clear notice protects entitlement to an extension of time. This template gives you a structure that covers the information the contract asks for. It does not reproduce the contract wording, so check the clauses in your own contract and any amendments.

What is included

  • Addressee, contract and notice reference fields
  • Material circumstances section
  • Cause of delay and Relevant Event
  • Expected effects on the Completion Date
  • Estimate of delay
  • Supporting documents schedule

How to use it

Using the JCT extension of time notice template on your project

  1. 01

    Give notice promptly

    Issue the notice as soon as the delay becomes reasonably apparent. Do not wait for the full picture.

  2. 02

    Describe the circumstances

    Explain what happened, when and how it affects the works.

  3. 03

    Identify the cause

    Name the Relevant Event where you consider one applies.

  4. 04

    Update as you go

    Provide further particulars and estimates as the effect becomes clearer.

Avoid these

Common mistakes we see on site

  • Waiting until the delay is fully known before giving notice
  • Notices with no link to the programme
  • Missing contract amendments that change notice periods
  • No records to support the estimate

Prefer us to handle it?

We can run this for you on site

Matthews & Roberts provides the people behind these templates: Temporary Works Coordinators, quantity surveyors, project managers and health and safety consultants across Liverpool, Manchester, the North West and North Wales.

Send us a message
Insights
View all insights

FAQ

JCT Extension of Time Notice Template: questions

When must a contractor give notice of delay under JCT?

When it becomes reasonably apparent that progress is being or is likely to be delayed. The notice should set out the material circumstances and identify any Relevant Event.

Which clause covers extension of time in JCT?

In the JCT Design and Build Contract 2016 the notice is under clause 2.24 and fixing the Completion Date under clause 2.25. In the Standard Building Contract 2016 the equivalent clauses are 2.27 and 2.28.

Is this template legal advice?

No. It is a practical template. Check your contract and amendments and take legal advice where the position is disputed.

Talk to us

Need support on your project?

Tell us about your site and what you need. We will come back within one working day with a clear proposal and a named consultant.

Call 0151 332 6581

Email info@matthewsroberts.com

3a Bridgwater Street, Baltic Triangle, Liverpool L1 0AR

Send us a message

Or call 0151 332 6581 or email info@matthewsroberts.com

We use your details only to reply to your enquiry.