What Is a Temporary Works Register and What Should It Include?

The temporary works register is the backbone of the BS 5975 procedure. Here is what it must include and how to stop it going out of date.

Matthews & Roberts2 min read
Construction drawings and temporary works register paperwork
On this page
  1. What the register should include
  2. Who maintains it
  3. Keeping it current
  4. Signs the register has drifted
  5. Register support in the North West
  6. Free template

A temporary works register is the live list of every temporary works item on a project and its status. It shows who designed each item, the check category, whether the design has been checked, whether it has been inspected and whether permits to load and strike have been issued. If an item is not on the register, nobody is controlling it.

What the register should include

  • Unique reference and description of the item
  • Location and the activity it supports
  • Designer and design reference
  • Check category, checker and certificate
  • Brief issued and design status
  • Installation date and inspection records
  • Permit to load and permit to strike references
  • Removal date and close out

Who maintains it

The Temporary Works Coordinator owns the register. Supervisors, designers and package managers feed information in. On larger projects the register may be shared digitally so everyone sees the current status.

Keeping it current

  1. 1Build it from the programme and method statements, not from what appears on site
  2. 2Review it at every progress meeting with package managers
  3. 3Add items before work starts, not after
  4. 4Close items only when they are removed and recorded

Signs the register has drifted

  • Items on site that are not on the register
  • Permits issued without a check certificate
  • Scaffolds altered with no record
  • Items still open long after removal

A temporary works audit will quickly show whether the register matches the site.

Register support in the North West

Matthews & Roberts sets up and manages temporary works registers for contractors in Liverpool, Manchester, Chester, Warrington and across the North West. See how a large register is run on our £2bn industrial scheme in Chester.

Free template

Download our free temporary works register template in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.

Need support on site? Matthews & Roberts provides Temporary Works Coordinator across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What is a temporary works register?

A live list of every temporary works item on a project, showing its designer, check category, design and check status, inspections and permits to load and strike.

Who is responsible for the temporary works register?

The Temporary Works Coordinator owns and maintains the register, with information from supervisors, designers and package managers.

How often should the register be reviewed?

Continuously as items change, with a formal review at regular project meetings so new items are captured before work starts.

Temporary works

Related guides and templates

The register links to design checks and permits. These cover each step.

Need support with temporary works on your project?

More insights

View all insights