Temporary Works

Temporary Works Design Check Categories Explained: Category 0, 1, 2 and 3

Every temporary works design needs the right level of independent check. Here is what BS 5975 Categories 0 to 3 mean and how to choose between them.

Matthews & Roberts1 min read
Temporary works design drawings prepared for an independent check
On this page
  1. The four categories
  2. Choosing the category
  3. Check certificates
  4. Common mistakes
  5. Support in the North West

BS 5975 sets four design check categories, from Category 0 for standard solutions to Category 3 for complex designs checked by a separate organisation. The higher the risk and complexity, the more independent the check must be.

The four categories

0

Typical use
Standard solutions from published guidance or manufacturer data
Who checks
Another member of the site or design team

1

Typical use
Simple designs
Who checks
Another member of the same design team

2

Typical use
More complex designs
Who checks
An individual not involved in the design and not consulted by the designer

3

Typical use
Complex or innovative designs
Who checks
A separate organisation

Choosing the category

The TWC and designer agree the category based on:

  • Complexity of the design and the analysis needed
  • Consequences of failure, including risk to the public
  • Novelty of the solution
  • Interfaces with existing structures or the permanent works

Typical Category 3 examples include facade retention, deep propped basements and large falsework schemes. Read about our Category 3 temporary works support.

Check certificates

Every check should produce a certificate recording the design, the checker, the category and any conditions. The certificate goes on the temporary works register before any permit to load is issued.

Common mistakes

  1. 1Category set too low to save time or cost
  2. 2Checks started after installation
  3. 3Changes on site made without returning to the designer and checker

Support in the North West

Matthews & Roberts coordinates temporary works design and checks for contractors in Liverpool, Manchester, Chester, Warrington and across the North West, alongside our temporary works design service. See also our BS 5975 guide.

Frequently asked questions

What is a Category 3 temporary works check?

A Category 3 check is for complex or innovative designs and must be carried out by a separate organisation from the designer.

Who decides the check category?

The Temporary Works Coordinator agrees the check category with the designer, based on the complexity and risk of the design.

What is a Category 0 check?

Category 0 applies to standard solutions where the design is taken from published guidance or a manufacturer's standard and checked by another member of the site or design team.

Temporary works

Related guides and templates

The category sets who checks the design. These cover the steps either side.

Need support with temporary works on your project?

More insights

View all insights