Free template · Contracts

NEC4 Compensation Event Notification Template

A free Word template for notifying a compensation event under NEC4, with sections for the event, the clause relied on, the expected effect, early warnings and timing.

Free to download, no sign up. White labelled so you can add your own company name and logo.

Need help using it?0151 332 6581info@matthewsroberts.com

Preview of the NEC4 compensation event notification template

About this template

What the NEC4 compensation event notification template is for

Under NEC4 clause 61.3 the Contractor notifies a compensation event within eight weeks of becoming aware that it has happened, unless the Project Manager should have notified it. Missing the window can mean losing the entitlement to more time and money.

This template helps your team give a clear, complete notification every time.

What is included

  • Notification reference, dates and linked early warning
  • The event and the clause relied on
  • Expected effect on the Prices, Completion and Key Dates
  • Early warning and timing statements
  • Space for the Project Manager's reply

How to use it

Using the NEC4 compensation event notification template on your project

  1. 01

    Notify within eight weeks

    Log the date you became aware and notify well within the window.

  2. 02

    Name the clause

    State which clause makes the event a compensation event.

  3. 03

    Describe the effect

    Explain the expected effect on cost and time.

  4. 04

    Prepare the quotation

    Be ready to submit a quotation when instructed.

Avoid these

Common mistakes we see on site

  • Notifying late and losing the entitlement
  • Vague descriptions that do not identify the event
  • No link to an early warning
  • Not tracking the Project Manager's reply period

Prefer us to handle it?

We can run this for you on site

Matthews & Roberts provides the people behind these templates: Temporary Works Coordinators, quantity surveyors, project managers and health and safety consultants across Liverpool, Manchester, the North West and North Wales.

Send us a message
Insights
View all insights

FAQ

NEC4 Compensation Event Notification Template: questions

How long does a contractor have to notify a compensation event under NEC4?

Eight weeks from becoming aware that the event has happened, under clause 61.3, unless the Project Manager should have notified it.

How long does the Project Manager have to reply?

Clause 61.4 gives the Project Manager one week to reply, or a longer period if agreed. If there is no reply, the contractor can notify the failure and the event may be treated as accepted.

Do you manage compensation events for contractors?

Yes. We manage early warnings, compensation events and quotations for contractors across the North West and North Wales.

Talk to us

Need support on your project?

Tell us about your site and what you need. We will come back within one working day with a clear proposal and a named consultant.

Call 0151 332 6581

Email info@matthewsroberts.com

3a Bridgwater Street, Baltic Triangle, Liverpool L1 0AR

Send us a message

Or call 0151 332 6581 or email info@matthewsroberts.com

We use your details only to reply to your enquiry.