Permit to Load and Permit to Strike Explained

Most temporary works incidents happen when items are first loaded or removed. Here is how permits to load and strike control both moments.

Matthews & Roberts2 min read
Tunnel construction where temporary works permits control loading and removal
On this page
  1. Permit to load
  2. Permit to strike
  3. Common mistakes
  4. Permits and client systems
  5. Permit control in the North West
  6. Free template

A permit to load authorises a temporary works item to be used. A permit to strike authorises its removal. Both are issued only after inspection. Both exist because the moments of first loading and final removal are when most temporary works fail.

Permit to load

Before a permit to load is issued, the TWC or an authorised supervisor checks that:

  • The design has been checked to the right category and the certificate is on the register
  • The installation matches the approved drawings
  • Materials and components are as specified and in good condition
  • Foundations and bearing are as designed
  • Any conditions from the designer or checker have been met

Permit to strike

Before a permit to strike is issued, the TWC checks that:

  • The permanent works can carry the load, for example concrete has reached the required strength
  • Removing the item will not destabilise anything else
  • The removal method and sequence are agreed
  • Other trades know the item is coming out

Common mistakes

  1. 1Loading before the permit is signed because the programme is tight
  2. 2Striking falsework early before concrete strength is confirmed
  3. 3Alterations after the permit without returning to the TWC
  4. 4Permits kept separately from the temporary works register

Permits and client systems

On industrial and operational sites, temporary works permits sit alongside the client's permit to work system. Agree how the two connect before work starts.

Permit control in the North West

Matthews & Roberts controls permits to load and strike as part of our Temporary Works Coordinator service in Liverpool, Manchester, Chester, Warrington and across the North West. See also falsework and back propping.

Free template

Download our free permit to load and strike templates in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.

Need support on site? Matthews & Roberts provides Temporary Works Coordinator across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

Who issues a permit to load?

The Temporary Works Coordinator, or a Temporary Works Supervisor authorised in writing by the TWC.

What must be checked before a permit to strike?

That the permanent works or another arrangement can safely carry the load, for example by confirming concrete strength. Removal must also not affect other temporary works.

Is a permit to strike the same as a permit to dismantle?

The terms are used for the same control: authorisation to remove temporary works once it is safe to do so.

Temporary works

Related guides and templates

Permits close out each item on the register. These cover the rest of the process.

Need support with temporary works on your project?

More insights

View all insights