Free template · Temporary works

Temporary Works Register Template

A free, editable Excel register for tracking every temporary works item on site, from the design brief and design check category to the permit to load and permit to strike.

Free to download, no sign up. White labelled so you can add your own company name and logo.

Need help using it?0151 332 6581info@matthewsroberts.com

Preview of the Temporary works register template

About this template

What the Temporary works register template is for

The temporary works register is the backbone of the procedure set out in BS 5975. It lists every item of temporary works on the project and shows, at a glance, where each one is in the process: brief issued, designed, checked, loaded, struck and closed.

This template gives your Temporary Works Coordinator a clean, consistent register that can be shared at every progress meeting. Add your own company name and project details and it is ready to use.

What is included

  • Project details block for the site, Principal Contractor and TWC
  • 60 pre numbered rows with a reference for every item
  • Design check category drop down (0 to 3)
  • Columns for design brief, design, checker and check certificate dates
  • Permit to load and permit to strike dates
  • Status drop down from brief issued to closed
  • Guidance tab explaining how to use the register

How to use it

Using the Temporary works register template on your project

  1. 01

    List every item

    Add each temporary works item as soon as the need is identified, from excavation support and propping to scaffolds, crane bases and hoardings.

  2. 02

    Set the category

    Agree the design check category with the designer. The category decides who can carry out the independent check.

  3. 03

    Track design and check

    Record the brief, the design and the check certificate. Nothing is installed until the design has been checked.

  4. 04

    Control loading and striking

    Only load an item once the permit to load is issued and only strike it once the permit to strike is issued.

  5. 05

    Review weekly

    Review the register at every progress meeting and close items once they are removed from site.

Avoid these

Common mistakes we see on site

  • Adding items only once they are on site rather than when the need is identified
  • Leaving the design check category blank until the design arrives
  • Allowing loading before the design check certificate is received
  • Not linking subcontractor temporary works into the main register

Prefer us to handle it?

We can run this for you on site

Matthews & Roberts provides the people behind these templates: Temporary Works Coordinators, quantity surveyors, project managers and health and safety consultants across Liverpool, Manchester, the North West and North Wales.

Send us a message

FAQ

Temporary Works Register Template: questions

What should a temporary works register include?

Every temporary works item on the project with its reference, description, location, design check category, design brief, design, check certificate, permits to load and strike and current status.

Who keeps the temporary works register?

The Temporary Works Coordinator is normally responsible for maintaining the register under the contractor's temporary works procedure.

Is a temporary works register a legal requirement?

The law requires temporary works to be managed safely under CDM 2015 and other regulations. BS 5975 sets out the recognised good practice, which includes keeping a register.

Can I edit this template?

Yes. The Excel file is fully editable and white labelled, so you can add your own logo and company details.

Talk to us

Need support on your project?

Tell us about your site and what you need. We will come back within one working day with a clear proposal and a named consultant.

Call 0151 332 6581

Email info@matthewsroberts.com

3a Bridgwater Street, Baltic Triangle, Liverpool L1 0AR

Send us a message

Or call 0151 332 6581 or email info@matthewsroberts.com

We use your details only to reply to your enquiry.