NEC4 Early Warning Register Template
A free Excel early warning register for NEC4 contracts. Record each matter, its potential effect on the Prices, Completion, a Key Date or performance and the actions agreed to reduce it.
Free to download, no sign up. White labelled so you can add your own company name and logo.
Need help using it?0151 332 6581info@matthewsroberts.com

About this template
What the NEC4 early warning register template is for
NEC4 asks the Project Manager and the Contractor to give early warning of anything that could increase the Prices, delay Completion or a Key Date or impair the performance of the works. The Early Warning Register records those matters and the actions agreed at early warning meetings.
This template gives both parties a clear, shared register with drop downs for the effects and status of each matter.
What is included
- 50 numbered early warning rows
- Yes or No drop downs for Prices, Completion, Key Date and performance
- Actions, owners and due dates
- Status and linked compensation event columns
- Guidance tab on using the register
Contract administration
Use the NEC4 early warning register template alongside these
Notices, programme and change all affect each other. These cover the related steps.
Guides
- NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and RecoveringNotifying and valuing compensation events under clause 60.
- NEC4 Early Warnings: A Contractor's Guide to Clause 15 and the Early Warning RegisterRaising early warnings under clause 15 and running the register.
- NEC4 Accepted Programme: What Clause 31 Requires and Why It Protects the ContractorGetting the programme accepted and keeping it current.
Free templates
- NEC4 Compensation Event Notification TemplateNotify a compensation event within the time bar.Free · Word and PDF
- JCT Extension of Time Notice TemplateA clear notice of delay with the facts recorded.Free · Word and PDF
- Request for Information (RFI) TemplateOne clear question, a due date and a register to track it.Free · Word and PDF
Where we have delivered this
Prefer us to run it for you? NEC4 contract administration
How to use it
Using the NEC4 early warning register template on your project
- 01
Notify early
Give an early warning as soon as you become aware of a matter.
- 02
Record it
Enter the matter, who notified it and its potential effects.
- 03
Agree actions
Discuss at the early warning meeting and record the decisions and owners.
- 04
Close it out
Remove matters once the risk has passed and link any resulting compensation event.
Avoid these
Common mistakes we see on site
- Treating the register as a list of claims
- Meetings held but actions not recorded
- Matters left open long after they have passed
- No link between early warnings and compensation events
Prefer us to handle it?
We can run this for you on site
Matthews & Roberts provides the people behind these templates: Temporary Works Coordinators, quantity surveyors, project managers and health and safety consultants across Liverpool, Manchester, the North West and North Wales.
Send us a messageRelated services
Services that go with this template
Free resources
More free construction templates
FAQ
NEC4 Early Warning Register Template: questions
Who keeps the NEC4 Early Warning Register?
The Project Manager maintains the register, but contractors often keep their own working copy and should check it is accurate.
What happens if an early warning is not given?
If an experienced contractor could have given an early warning and did not, the compensation event may be assessed as if it had been given.
Is the Early Warning Register the same as a risk register?
It overlaps, but the Early Warning Register records the specific matters notified under the contract and the actions agreed.
Talk to us
Need support on your project?
Tell us about your site and what you need. We will come back within one working day with a clear proposal and a named consultant.
Email info@matthewsroberts.com
3a Bridgwater Street, Baltic Triangle, Liverpool L1 0AR