On this page
Appointing a Temporary Works Coordinator is one of the most important safety decisions a contractor makes on a project. The TWC controls the process that keeps excavations, propping, falsework, working platforms and other temporary works safe from design through to removal.
This checklist sets out what to confirm before and after you make the appointment. It follows the principles of BS 5975 and is written for contractors working across Liverpool, Manchester and the wider North West, although it applies to any UK project.
Download the printable checklist (PDF)
Before you appoint
1. Confirm the need
- More than one item of temporary works is planned, or a single item carries significant risk
- Several packages or subcontractors will install or rely on temporary works
- Temporary works interact with existing structures, live services or the public highway
If any of these apply, appoint a TWC before the first item of temporary works is designed.
2. Check competence
- Relevant training to an appropriate standard for the role
- Experience of temporary works similar in scale and complexity to the project
- Understanding of design check categories 0 to 3 and when independent checks are required
- Confidence to stop work when an item is not safe to load or strike
3. Define the scope
- The project, phase or packages covered
- Whether the TWC covers design coordination, site control or both
- How many Temporary Works Supervisors are needed and who appoints them
- How the TWC interfaces with other contractors' coordinators on shared sites
4. Put the appointment in writing
- Formal appointment by the Designated Individual
- Clear authority to stop work
- Reporting line and escalation route
- The temporary works procedure the TWC will operate
Once the TWC is in place
5. The temporary works register
- Every item recorded with its designer, check category, status and permits
- The register reviewed at programme meetings so upcoming items are planned well ahead
- Changes to the sequence reflected in the register straight away
6. Design briefs and checks
- A design brief for each item setting out loads, constraints, ground conditions and interfaces
- Design check category agreed before design starts
- Independent check certificates received before construction
7. Installation and permits
- Inspection of each installation against the approved design
- Permit to load issued only once the installation is confirmed
- Permit to strike issued only once the permanent works can carry the load
- Records and photographs held with the register
8. Change and handover
- A clear route for any change to an approved design
- Handover of the register and records if the TWC changes during the project
- Lessons recorded at the end of the project for the next job
How this works on North West projects
Constrained sites in Liverpool and Manchester city centres often place temporary works next to occupied buildings, live services and busy streets. Larger industrial schemes across Cheshire and the wider North West can carry hundreds of items at the higher check categories. In both cases the register and the permit system are what keep control, so they should be in place from the start.
Our full guide to BS 5975 explains the standard in more detail. You can also see how a large register is run in our £2bn industrial scheme case study.
Related reading: temporary works coordination best practice and temporary works on Liverpool city centre sites.
Related reading: what a Temporary Works Coordinator does, TWC vs TWS and TWC training.
Matthews & Roberts provides independent Temporary Works Coordinator services and temporary works design to contractors across the North West. Get in touch to discuss an appointment.
Free template
Download our free TWC appointment checklist in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.
Need support on site? Matthews & Roberts provides Temporary Works Coordinator across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.
Frequently asked questions
Who appoints the Temporary Works Coordinator?
The contractor's Designated Individual appoints the Temporary Works Coordinator in writing. On projects with several contractors the Principal Contractor's TWC holds overall responsibility for temporary works on site, with other contractors working within that procedure.
Can a Temporary Works Coordinator be external to the contractor?
Yes. BS 5975 allows the TWC to be an external appointment provided the person is competent, has the authority to stop work and is formally appointed by the organisation. Many contractors use an external TWC on larger or more complex schemes.
What should be in a TWC appointment letter?
The scope of the appointment, the project or packages covered, the authority to stop work, the reporting line to the Designated Individual, the procedure to be followed and any Temporary Works Supervisors appointed to support the TWC.
Temporary works
Related guides and templates
Temporary works procedures link together. These guides and templates cover the rest of the process.
Guides
- BS 5975 Explained: The Contractor's Guide to Temporary Works ProceduresThe code of practice behind every temporary works procedure.
- What Does a Temporary Works Coordinator Do?The TWC role day to day.
- Temporary Works Coordinator vs Temporary Works Supervisor: What Is the Difference?How the TWC and TWS roles divide the work.
- What Does a Temporary Works Supervisor Do?The TWS role on site.
Free templates
- Temporary Works Coordinator Appointment ChecklistCompetence, appointment and systems checks for a TWC.Free · Word and PDF
- Temporary Works Register TemplateExcel register with categories, checks and permits.Free · Excel and PDF
- Permit to Load & Permit to Strike TemplatesPermit forms ready to issue on site.Free · Word and PDF
Need support with temporary works on your project?




