Excavation support is temporary works that keeps the sides of an excavation stable while people work in or near it. It ranges from simple trench boxes to designed sheet pile cofferdams and propped basements. CDM 2015 requires every excavation to be prevented from collapsing and to be inspected by a competent person.
Types of excavation support
| Type | Typical use |
|---|---|
| Battering or stepping | Open sites with space and suitable ground |
| Trench boxes and drag boxes | Drainage and service trenches |
| Hydraulic frames and shores | Narrow trenches |
| Sheet piles | Deep or water bearing excavations |
| Cofferdams | Excavations below groundwater or in water |
| Propped excavations | Basements next to buildings or roads |
Battering or stepping
- Typical use
- Open sites with space and suitable ground
Trench boxes and drag boxes
- Typical use
- Drainage and service trenches
Hydraulic frames and shores
- Typical use
- Narrow trenches
Sheet piles
- Typical use
- Deep or water bearing excavations
Cofferdams
- Typical use
- Excavations below groundwater or in water
Propped excavations
- Typical use
- Basements next to buildings or roads
When a design is needed
Proprietary systems still need selecting for the depth, ground and surcharge. A full design and independent check are needed for bespoke schemes, deep excavations and anything near structures, roads or railways. Read about check categories.
CDM 2015 inspection rules
Excavations must be inspected by a competent person at the start of each shift, after any event likely to affect stability and after any accidental fall of material. Inspections must be recorded.
Hazards to plan for
- Surcharge from plant, spoil heaps and adjacent structures
- Groundwater and the effect of dewatering on nearby buildings
- Buried services. Follow HSG47.
- Falls of people, plant and materials into the excavation
- Safe access and egress
Linked guides
See what counts as temporary works and our BS 5975 guide.
Excavation support coordination in the North West
Matthews & Roberts coordinates excavation support temporary works for contractors in Liverpool, Manchester, Chester, Warrington, Wigan, St Helens and across the North West. See our Tatton Services M56 case study.
Frequently asked questions
How often should excavations be inspected?
CDM 2015 requires inspection by a competent person at the start of each shift, after any event likely to affect stability and after any accidental fall of rock or material.
When does excavation support need a design?
Bespoke schemes, deep excavations, excavations near structures or roads and anything outside the supplier's standard guidance need a design and an independent check.
What is the safest way to avoid buried services?
Follow HSG47: plan the work using records, locate and mark services with detection equipment and use safe digging methods near known services.
Temporary works
Related guides and templates
Temporary works procedures link together. These guides and templates cover the rest of the process.
Guides
- BS 5975 Explained: The Contractor's Guide to Temporary Works ProceduresThe code of practice behind every temporary works procedure.
- Facade Retention Temporary Works: How Historic Facades Are Kept StableRetaining a facade safely while the building behind is rebuilt.
- Temporary Works Coordination: Best Practice GuidanceEffective temporary works management is critical to construction safety. Learn the key principles and how proper...
- What Training Does a Temporary Works Coordinator Need?Training is only part of TWC competence. Here is what courses are available, what experience matters and how to...
Free templates
- Excavation Inspection Register TemplateShift start and post event inspection records.Free · Excel and PDF
- Temporary Works Register TemplateExcel register with categories, checks and permits.Free · Excel and PDF
- Temporary Works Coordinator Appointment ChecklistCompetence, appointment and systems checks for a TWC.Free · Word and PDF
Need support with temporary works on your project?