Temporary Works

Excavation Support Temporary Works: Trench Boxes, Sheet Piles and Inspections

Excavations collapse without warning. Here is how excavation support works, when it needs a design and what CDM 2015 requires.

Matthews & Roberts1 min read
Highway infrastructure scheme with excavation support temporary works
On this page
  1. Types of excavation support
  2. When a design is needed
  3. CDM 2015 inspection rules
  4. Hazards to plan for
  5. Linked guides
  6. Excavation support coordination in the North West

Excavation support is temporary works that keeps the sides of an excavation stable while people work in or near it. It ranges from simple trench boxes to designed sheet pile cofferdams and propped basements. CDM 2015 requires every excavation to be prevented from collapsing and to be inspected by a competent person.

Types of excavation support

Battering or stepping

Typical use
Open sites with space and suitable ground

Trench boxes and drag boxes

Typical use
Drainage and service trenches

Hydraulic frames and shores

Typical use
Narrow trenches

Sheet piles

Typical use
Deep or water bearing excavations

Cofferdams

Typical use
Excavations below groundwater or in water

Propped excavations

Typical use
Basements next to buildings or roads

When a design is needed

Proprietary systems still need selecting for the depth, ground and surcharge. A full design and independent check are needed for bespoke schemes, deep excavations and anything near structures, roads or railways. Read about check categories.

CDM 2015 inspection rules

Excavations must be inspected by a competent person at the start of each shift, after any event likely to affect stability and after any accidental fall of material. Inspections must be recorded.

Hazards to plan for

  • Surcharge from plant, spoil heaps and adjacent structures
  • Groundwater and the effect of dewatering on nearby buildings
  • Buried services. Follow HSG47.
  • Falls of people, plant and materials into the excavation
  • Safe access and egress

Linked guides

See what counts as temporary works and our BS 5975 guide.

Excavation support coordination in the North West

Matthews & Roberts coordinates excavation support temporary works for contractors in Liverpool, Manchester, Chester, Warrington, Wigan, St Helens and across the North West. See our Tatton Services M56 case study.

Frequently asked questions

How often should excavations be inspected?

CDM 2015 requires inspection by a competent person at the start of each shift, after any event likely to affect stability and after any accidental fall of rock or material.

When does excavation support need a design?

Bespoke schemes, deep excavations, excavations near structures or roads and anything outside the supplier's standard guidance need a design and an independent check.

What is the safest way to avoid buried services?

Follow HSG47: plan the work using records, locate and mark services with detection equipment and use safe digging methods near known services.

Temporary works

Related guides and templates

Temporary works procedures link together. These guides and templates cover the rest of the process.