Temporary Works

Temporary Works Coordinator vs Temporary Works Supervisor: What Is the Difference?

TWC and TWS are often confused. Here is how the two BS 5975 roles differ, how they work together and when a project needs both.

Matthews & Roberts1 min read
Site engineer and operative checking temporary works on a North West project
On this page
  1. Side by side
  2. When you need both
  3. Training
  4. TWC and TWS support in the North West

The Temporary Works Coordinator manages the temporary works process. The Temporary Works Supervisor controls the work at the workface. Both roles come from BS 5975 and they work together, but they are not the same job.

Side by side

Focus

Temporary Works Coordinator
The whole procedure for the project
Temporary Works Supervisor
Installation, use and removal at the workface

Register

Temporary Works Coordinator
Owns and maintains it
Temporary Works Supervisor
Feeds information into it

Designs

Temporary Works Coordinator
Briefs designers and ensures checks
Temporary Works Supervisor
Checks installation against the design

Permits

Temporary Works Coordinator
Issues permits to load and strike
Temporary Works Supervisor
May issue them only if authorised by the TWC

Appointment

Temporary Works Coordinator
By the Designated Individual
Temporary Works Supervisor
By the organisation, in agreement with the TWC

When you need both

  • Large sites with many temporary works items
  • Several packages or subcontractors with their own temporary works
  • Shift work or out of hours operations
  • High risk items such as facade retention or deep excavation support

Training

Both roles normally hold recognised training. CITB runs a Temporary Works Coordinator course and a Temporary Works Supervisor course. Read our guide to temporary works training courses.

TWC and TWS support in the North West

Matthews & Roberts provides Temporary Works Coordinators and Temporary Works Supervisors to contractors in Liverpool, Manchester, Chester, Warrington and across the North West. Read what a Temporary Works Coordinator does.

Frequently asked questions

What is the difference between a TWC and a TWS?

The Temporary Works Coordinator manages the temporary works procedure for the project. The Temporary Works Supervisor works under the TWC and controls installation, use and removal of temporary works at the workface.

Can a TWS issue permits?

Only where the TWC has authorised them to do so in writing. Otherwise the TWC issues permits to load and strike.

Does every project need a TWS?

Not always. On smaller projects the TWC may cover supervision. Larger sites or several packages usually need one or more supervisors.

Temporary works

Related guides and templates

Temporary works procedures link together. These guides and templates cover the rest of the process.

Need support with temporary works on your project?

More insights

View all insights