Facade retention keeps the external walls of an existing building in place while the structure behind them is demolished and rebuilt. A temporary structure holds the facade until the new frame can take over. Because a failure can be catastrophic and the public is often close by, retention schemes need careful design, independent checking and constant monitoring.
The stages of a retention scheme
- 1Survey: record the condition of the facade, ties, openings and existing structure
- 2Design: the retention structure is designed for wind, self weight and construction loads
- 3Check: usually a high check category, often Category 3
- 4Installation: the retention structure is installed and tied before demolition begins
- 5Monitoring: movement is measured against agreed trigger levels
- 6Transfer: the facade is tied into the new frame, then the retention structure is removed under a permit to strike
Types of retention structure
- Internal: inside the building footprint, keeping the street clear
- External: on the pavement or highway, needing a licence
- Combined: a mix of both, common on tight city centre sites
Key risks
- Wind loading on a free standing facade
- Weak or deteriorated masonry and ties
- Vibration from demolition
- Changes to the sequence on site
Heritage requirements
Listed buildings and conservation areas bring planning and heritage conditions that affect the scheme. Agree them before design starts. See our guide to temporary works on Liverpool city centre sites and historic barns on the M56.
Facade retention coordination in the North West
Matthews & Roberts coordinates facade retention temporary works for contractors in Liverpool, Chester, Manchester, Stockport and across the North West.
Frequently asked questions
How long can a facade be retained?
As long as the retention structure is designed for. Schemes are designed for a specific duration and loads, including wind, so extending the period needs review by the designer.
What monitoring is needed for facade retention?
Movement monitoring of the facade and the retention structure with agreed trigger levels and actions, reviewed regularly through the works.
What guidance covers facade retention?
CIRIA C579 on the retention of masonry facades is widely used, alongside BS 5975 for the temporary works procedure.
Temporary works
Related guides and templates
Temporary works procedures link together. These guides and templates cover the rest of the process.
Guides
- BS 5975 Explained: The Contractor's Guide to Temporary Works ProceduresThe code of practice behind every temporary works procedure.
- Temporary Works Coordination: Best Practice GuidanceEffective temporary works management is critical to construction safety. Learn the key principles and how proper...
- What Training Does a Temporary Works Coordinator Need?Training is only part of TWC competence. Here is what courses are available, what experience matters and how to...
- Temporary Works on Liverpool City Centre Sites: What Contractors Should Plan ForLiverpool city centre sites are tight, surrounded by occupied and historic buildings and close to busy streets. This...
Free templates
- Temporary Works Register TemplateExcel register with categories, checks and permits.Free · Excel and PDF
- Temporary Works Coordinator Appointment ChecklistCompetence, appointment and systems checks for a TWC.Free · Word and PDF
- Permit to Load & Permit to Strike TemplatesPermit forms ready to issue on site.Free · Word and PDF
Need support with temporary works on your project?