A temporary works design brief tells the designer what the temporary works must do, the conditions it will work in and the constraints it must meet. Most redesigns and delays trace back to a brief with missing information.
What to include
| Section | Content |
|---|---|
| Purpose | What the temporary works will support or retain and for how long |
| Site information | Location, access, neighbouring structures, services |
| Ground data | Site investigation results and groundwater levels |
| Loads | Construction, plant, storage and environmental loads |
| Sequence | Installation, use, adaptation and removal |
| Constraints | Space, noise, vibration, interfaces with permanent works |
| Check category | Agreed with the designer, 0 to 3 under BS 5975 |
| Dates | When the design, check and installation are needed |
Purpose
- Content
- What the temporary works will support or retain and for how long
Site information
- Content
- Location, access, neighbouring structures, services
Ground data
- Content
- Site investigation results and groundwater levels
Loads
- Content
- Construction, plant, storage and environmental loads
Sequence
- Content
- Installation, use, adaptation and removal
Constraints
- Content
- Space, noise, vibration, interfaces with permanent works
Check category
- Content
- Agreed with the designer, 0 to 3 under BS 5975
Dates
- Content
- When the design, check and installation are needed
Common gaps
- No ground investigation data for excavation support
- Plant loads near excavations missed
- Sequence that does not match how the site will build
- Check category left until the design arrives
Where the brief fits
The brief is issued by the Temporary Works Coordinator and recorded in the temporary works register. The design is then checked at the right category before permits to load are issued.
Temporary works design support
Matthews & Roberts arranges temporary works design and independent design checks through our engineering partners in Liverpool, Manchester, Chester and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.
Frequently asked questions
What is a temporary works design brief?
The document that tells the designer what the temporary works must do, the site conditions, loads, constraints and the check category.
Who writes the design brief?
Usually the person who needs the temporary works, reviewed and issued by the Temporary Works Coordinator.
Why does the brief matter?
Missing or wrong information leads to redesign, delay or an unsafe design. A good brief gets the design right first time.
Temporary works
Related guides and templates
Temporary works procedures link together. These guides and templates cover the rest of the process.
Guides
- BS 5975 Explained: The Contractor's Guide to Temporary Works ProceduresThe code of practice behind every temporary works procedure.
- Who Can Design Temporary Works? Designers, Checkers and CompetenceCompetence for temporary works designers.
- What Counts as Temporary Works? Examples on Construction SitesCommon items that need to be on the register.
- Excavation Support Temporary Works: Trench Boxes, Sheet Piles and InspectionsTrench and excavation support from design to inspection.
Free templates
- Temporary Works Design Brief TemplateEverything the designer needs in one brief.Free · Word and PDF
- Temporary Works Register TemplateExcel register with categories, checks and permits.Free · Excel and PDF
- Temporary Works Coordinator Appointment ChecklistCompetence, appointment and systems checks for a TWC.Free · Word and PDF
Need support with temporary works design on your project?