Quantity Surveying

Client Side vs Contractor Side Quantity Surveyor: What Is the Difference?

Both roles measure and value construction work, but they protect different things. One protects the budget. The other protects the margin. Here is how they differ and when you need each.

Matthews & Roberts4 min read
Quantity surveyors reviewing drawings and cost information on a construction project
On this page
  1. What a client side quantity surveyor does
  2. What a contractor side quantity surveyor does
  3. The key differences at a glance
  4. How this relates to commercial management
  5. When you need each one
  6. Free templates for both sides
  7. Quantity surveyors across the North West and North Wales

A client side quantity surveyor protects the budget. A contractor side quantity surveyor protects the margin. Both measure and value construction work, but they work for different parties, answer different questions and produce different documents.

If you are a client, developer or funder, you need someone who can tell you what the project should cost and stop you paying for work that has not been done. If you are a main contractor or subcontractor, you need someone who makes sure you are paid for everything you deliver, including the change you are asked to carry out.

What a client side quantity surveyor does

The client side quantity surveyor, sometimes called a cost consultant or PQS, advises the employer from the first budget to the final account.

Before construction

  • Estimates and cost plans. An order of cost estimate at feasibility, then an elemental cost plan to NRM1 as the design develops. See our cost plans and estimating service.
  • Procurement advice. Recommending a route such as traditional, design and build or two stage.
  • Tender documents and analysis. Bills of quantities or pricing schedules, then a tender report that compares returns on a like for like basis.

During construction

  • Valuations and payment certificates. Checking each contractor application against the work on site and recommending the sum to certify.
  • Change control. Pricing change before it is instructed so the client decides with the cost in view.
  • Cost reports. A monthly report to the client and any funder showing budget, approved change, committed cost and forecast final cost.

At the end

  • Final account agreement. Reviewing the contractor's account line by line and agreeing a fair figure on the evidence.

Our client side quantity surveying page explains how we provide this for clients across the North West and North Wales.

What a contractor side quantity surveyor does

The contractor side quantity surveyor works for the main contractor or a subcontractor. Their job is to make sure the value of the work is captured, the supply chain is bought well and the money comes in.

  • Take offs and tender pricing. Quantities for the bid and for subcontract enquiries.
  • Subcontract procurement. Package enquiries, tender comparisons and buy out against the tender allowance.
  • Applications for payment. Monthly applications built from measured progress and agreed change.
  • Variations and compensation events. Change notified, priced and tracked to agreement under JCT or NEC4.
  • Subcontract accounts. Valuations, payment notices and final accounts for every package.
  • Cost reporting. Value and liabilities feeding the monthly cost value reconciliation.
  • Final account. Prepared and negotiated with the evidence to support every line.

See what a quantity surveyor does for contractors for more detail.

The key differences at a glance

Works for

Client side QS
Client, developer or funder
Contractor side QS
Main contractor or subcontractor

Main aim

Client side QS
Keep the project within budget
Contractor side QS
Protect margin and cash flow

Early stage work

Client side QS
Estimates, cost plans, tender documents
Contractor side QS
Take offs, tender pricing, package buy out

Monthly work

Client side QS
Valuations, certificates, cost reports
Contractor side QS
Applications, change, subcontract accounts, CVR input

Change

Client side QS
Priced and approved before instruction
Contractor side QS
Notified, priced and recovered

End of job

Client side QS
Agree a fair final account
Contractor side QS
Secure the full final account

How this relates to commercial management

On the contractor side, a commercial manager usually leads the commercial function and takes responsibility for the overall position, while quantity surveyors carry out the day to day work. Our guide to the quantity surveyor vs commercial manager covers that split.

On the client side the equivalent is cost management: keeping the budget, contingency and forecast under control across the project. Our cost and commercial management service covers both sides.

When you need each one

You need a client side quantity surveyor if you are funding or developing a project and need a reliable budget, a fair tender process, independent payment certification or reporting for a lender.

You need a contractor side quantity surveyor if you are building the project and need applications, change and subcontract accounts kept up to date, or a final account closed out.

You may need both if you are a developer who also builds. In that case keep the roles separate on each contract so the advice stays independent.

Free templates for both sides

We publish free templates for each role in our commercial resources:

Quantity surveyors across the North West and North Wales

Matthews & Roberts provides client side and contractor side quantity surveying from our Liverpool office. We support projects in Liverpool, Manchester, Chester and Cheshire, Warrington and Preston, as well as Wrexham, Deeside and Flintshire and the rest of North Wales.

Commercial control has formed part of our role on projects such as the Pharmaron gene therapy facility in Liverpool and the Stamford Arms heritage residential scheme in Cheshire.

Need a quantity surveyor on either side of the contract? Call 0151 332 6581, email info@matthewsroberts.com or see our quantity surveying service.

Frequently asked questions

What does a client side quantity surveyor do?

A client side quantity surveyor advises the client on cost. That covers estimates and cost plans, procurement and tender reports, valuing and certifying contractor payments, change control, monthly cost reports and agreeing the final account.

What does a contractor side quantity surveyor do?

A contractor side quantity surveyor manages the contractor's commercial position. That covers take offs, subcontract procurement, applications for payment, variations, subcontract accounts, input to the CVR and the final account.

Is a cost consultant the same as a quantity surveyor?

Usually a cost consultant is a client side quantity surveyor. The title is often used by firms that provide cost planning and cost management to clients and developers.

What is a PQS?

PQS stands for professional quantity surveyor. It is an older term for a client side or consultant quantity surveyor, as opposed to a contractor's quantity surveyor.

Can one firm act on both sides?

Yes, but never on both sides of the same contract. A firm with experience on both sides knows how each account is built and challenged, which makes its advice more realistic.

Commercial control

Related guides and templates

A commercial review draws on more than one record. These guides and templates support it.

Need support with quantity surveying on your project?

More insights

View all insights