How Are Construction Variations Valued? A Guide for Contractors

Variations are where most contractors lose value. Here is how change is valued under JCT and NEC4 and how to make sure you are paid for it.

Matthews & Roberts2 min read
Contractor commercial team valuing a construction variation
On this page
  1. Step one: identify the change
  2. Step two: notify on time
  3. Step three: value it
  4. Step four: support it with records
  5. Step five: agree it during the job
  6. Help with variations in the North West

Construction variations are valued using the rules in the contract. Under JCT that usually means contract rates, adjusted rates or fair rates. Under NEC4 it means assessing the effect of a compensation event on Defined Cost plus the Fee. Whatever the contract, the contractor that records and notifies change promptly gets paid for more of it.

Step one: identify the change

Change arrives in many forms: formal instructions, revised drawings, answers to technical queries, site conversations and discovered conditions. Every one should go on a change register the day it appears. Read about our variations and change control service.

Step two: notify on time

Contracts set notice requirements. Under NEC4, failing to notify a compensation event within eight weeks of becoming aware can remove entitlement in many cases. JCT contracts have their own notice provisions. Late notice is one of the most common reasons value is lost. See our NEC4 compensation events guide.

Step three: value it

Under JCT

Similar work under similar conditions

Usual basis
Contract rates

Similar work under different conditions

Usual basis
Contract rates adjusted for the difference

Work not similar to anything in the contract

Usual basis
Fair rates and prices

Work that cannot properly be measured

Usual basis
Daywork

Read our guide to daywork sheets for when daywork applies.

Under NEC4

Compensation events are assessed on the forecast or actual effect on Defined Cost plus the Fee, together with any delay to the planned Completion date. The contractor usually submits a quotation with a revised programme.

Step four: support it with records

Labour and plant allocation sheets, material invoices, photos before and after, drawing revisions and programme analysis all help. The other side can only agree what it can check.

Step five: agree it during the job

Variations agreed month by month make the final account simple. Variations left to the end become disputes.

Help with variations in the North West

Matthews & Roberts provides quantity surveyors who value change for contractors and subcontractors in Manchester, Liverpool, Stockport, St Helens and across the North West.

Frequently asked questions

How are variations valued under JCT?

JCT valuation rules use contract rates where the varied work is similar to contract work, adjusted rates where conditions differ and fair rates and prices where there is nothing comparable. Daywork applies where work cannot properly be measured.

How are compensation events valued under NEC4?

Compensation events are assessed on their effect on Defined Cost plus the Fee and on the planned Completion date, usually through a quotation prepared by the contractor.

What records support a variation?

The instruction or event, drawings, photos, labour and plant records, material invoices, programme impact and a clear build up of the price.

Commercial control

Related guides and templates

Valued variations flow into the application, the CVR and the final account.