On this page
Construction variations are valued using the rules in the contract. Under JCT that usually means contract rates, adjusted rates or fair rates. Under NEC4 it means assessing the effect of a compensation event on Defined Cost plus the Fee. Whatever the contract, the contractor that records and notifies change promptly gets paid for more of it.
Step one: identify the change
Change arrives in many forms: formal instructions, revised drawings, answers to technical queries, site conversations and discovered conditions. Every one should go on a change register the day it appears. Read about our variations and change control service.
Step two: notify on time
Contracts set notice requirements. Under NEC4, failing to notify a compensation event within eight weeks of becoming aware can remove entitlement in many cases. JCT contracts have their own notice provisions. Late notice is one of the most common reasons value is lost. See our NEC4 compensation events guide.
Step three: value it
Under JCT
| Situation | Usual basis |
|---|---|
| Similar work under similar conditions | Contract rates |
| Similar work under different conditions | Contract rates adjusted for the difference |
| Work not similar to anything in the contract | Fair rates and prices |
| Work that cannot properly be measured | Daywork |
Similar work under similar conditions
- Usual basis
- Contract rates
Similar work under different conditions
- Usual basis
- Contract rates adjusted for the difference
Work not similar to anything in the contract
- Usual basis
- Fair rates and prices
Work that cannot properly be measured
- Usual basis
- Daywork
Read our guide to daywork sheets for when daywork applies.
Under NEC4
Compensation events are assessed on the forecast or actual effect on Defined Cost plus the Fee, together with any delay to the planned Completion date. The contractor usually submits a quotation with a revised programme.
Step four: support it with records
Labour and plant allocation sheets, material invoices, photos before and after, drawing revisions and programme analysis all help. The other side can only agree what it can check.
Step five: agree it during the job
Variations agreed month by month make the final account simple. Variations left to the end become disputes.
Help with variations in the North West
Matthews & Roberts provides quantity surveyors who value change for contractors and subcontractors in Manchester, Liverpool, Stockport, St Helens and across the North West.
Frequently asked questions
How are variations valued under JCT?
JCT valuation rules use contract rates where the varied work is similar to contract work, adjusted rates where conditions differ and fair rates and prices where there is nothing comparable. Daywork applies where work cannot properly be measured.
How are compensation events valued under NEC4?
Compensation events are assessed on their effect on Defined Cost plus the Fee and on the planned Completion date, usually through a quotation prepared by the contractor.
What records support a variation?
The instruction or event, drawings, photos, labour and plant records, material invoices, programme impact and a clear build up of the price.
Commercial control
Related guides and templates
Valued variations flow into the application, the CVR and the final account.
Guides
- Cost Value Reconciliation in Construction: A Contractor's Guide to CVRHow to compare cost with value and report the margin honestly.
- How to Prepare an Interim Payment Application in ConstructionBuilding an application that is easy to agree and quick to pay.
- What Is a Construction Final Account and How Do You Agree One?Closing out the account with the evidence to back every line.
- What Are Daywork Sheets and When Can You Use Daywork in Construction?Recording daywork so it is signed, priced and recoverable.
Free templates
- Variation and Change Register TemplateEvery change logged with values that feed the CVR.Free · Excel and PDF
- Construction CVR TemplateMonthly cost and value by package with margin and forecast.Free · Excel and PDF
- Bill of Quantities TemplateItems by NRM2 section with automatic totals.Free · Excel and PDF
Need support with quantity surveying on your project?