Cost Value Reconciliation in Construction: A Contractor's Guide to CVR

A cost value reconciliation shows whether a project is really making money. This guide explains how a construction CVR works and what contractors should look for each month.

Matthews & Roberts2 min read
Quantity surveyors reviewing a construction cost value reconciliation
On this page
  1. Why the CVR matters
  2. The value side
  3. The cost side
  4. Reconciling the two
  5. What a good monthly CVR shows
  6. Common problems
  7. Free template

A cost value reconciliation (CVR) compares the value a contractor has earned with the cost of earning it, at the same point in time. Done properly each month, it shows whether a project is really making money and where margin is moving.

Why the CVR matters

The amount applied for and the amount spent rarely tell the full story on their own. Work done but not yet applied for, costs incurred but not yet invoiced and change that is still unpriced all distort the picture. The CVR adjusts for these so the reported margin reflects reality.

The value side

  • Gross valuation to date, from the latest application or measure
  • Adjustments for over or under measurement
  • Value of change instructed but not yet agreed, assessed realistically
  • Deductions for items at risk, such as disputed variations or defects

The cost side

  • Costs posted to date in the accounts
  • Accruals for work done but not yet invoiced, such as subcontractor and plant costs
  • Liabilities for committed but unrecorded costs
  • Provisions for known risks and costs to complete defects

Reconciling the two

Value less cost gives the margin to date. Compare it with the tender margin and the previous month. A falling margin is an early warning: investigate whether value is understated, cost is overstated or the project genuinely has a problem.

What a good monthly CVR shows

  1. 1Margin to date against tender and last month
  2. 2A forecast of final cost and final value
  3. 3Key movements explained in plain terms
  4. 4Risks and opportunities with values attached
  5. 5Actions to protect margin

Common problems

  • Accruals missed or double counted
  • Unpriced change left out of value, or included at full value without evidence
  • Subcontractor liabilities not reconciled to their accounts
  • Forecasts not updated as the programme moves

Related reading: payment notices for subcontractors and NEC4 compensation events.

Related reading: what a quantity surveyor does for a contractor, how variations are valued and agreeing the final account. We provide quantity surveyors in Manchester, Liverpool and across the North West.

Matthews & Roberts provides commercial and cost management and quantity surveying services for main contractors and subcontractors across Liverpool, the North West and the UK.

Free template

Download our free CVR template in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.

Need support on site? Matthews & Roberts provides commercial management across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What is a cost value reconciliation in construction?

A cost value reconciliation, or CVR, compares the value a contractor has earned on a project with the cost of earning it, at the same date. The difference is the true margin, after adjusting for accruals, liabilities and risk.

How often should a CVR be done?

Most contractors carry out a CVR monthly, aligned with the valuation and the accounts period, so margin movement is spotted early.

Commercial control

Related guides and templates

A CVR is only as strong as the records behind it. These support the review and the client report.

Need support with commercial & cost management on your project?

More insights

View all insights