On this page
A construction final account is the agreed total value of the contract. It starts with the original contract sum and adjusts it for every variation, provisional sum, fluctuation and agreed claim. Until it is agreed, money and retention stay tied up.
What goes into a final account
- The contract sum as originally agreed
- Variations or compensation events valued under the contract rules
- Provisional sums omitted and replaced with the actual cost of the work
- Fluctuations where the contract allows them
- Loss and expense where entitlement has been established
- Deductions for damages or other contract adjustments
Contract time limits
JCT and NEC contracts set time limits for submitting documents, issuing the final statement or certificate and raising disputes. Missing them can make the final figures conclusive. Diary every date at the start of the project.
Why final accounts get stuck
- 1Change was never agreed during the project
- 2Records are missing, especially for daywork and discovered conditions. See our daywork guide.
- 3Subcontract accounts are still open, so the main account cannot close
- 4Disputes about entitlement rather than value
How to close the account
- Agree variations every month. See how variations are valued.
- Keep the change register and supporting evidence in one place
- Close subcontract accounts first
- Separate disputes about value from disputes about entitlement
- Meet face to face to work through the open items
Retention and the final account
Most contracts release the second half of retention at the end of the defects or rectification period, often linked to the final account. Read retention in construction contracts.
Final account support in the North West
Matthews & Roberts prepares and agrees construction final accounts for contractors and subcontractors in Warrington, Salford, Chester, Liverpool and across the North West.
Frequently asked questions
What is included in a final account?
The contract sum adjusted for variations, provisional sums, fluctuations where they apply, any agreed loss and expense and any other contract adjustments.
Why do final accounts take so long?
Usually because change was not agreed during the project, records are incomplete or there are disputes about entitlement. Accounts with change agreed monthly close much faster.
What happens if a final account cannot be agreed?
The parties can negotiate further, use mediation or refer the dispute to adjudication. Clear records and early agreement of change reduce the risk.
Commercial control
Related guides and templates
A final account is built from the records kept during the job. These help you assemble them.
Guides
- Cost Value Reconciliation in Construction: A Contractor's Guide to CVRHow to compare cost with value and report the margin honestly.
- What Are Daywork Sheets and When Can You Use Daywork in Construction?Recording daywork so it is signed, priced and recoverable.
- Payment Notices and Applications: A Quantity Surveying Guide for Liverpool SubcontractorsPayment and pay less notices that protect your cash flow.
- How Does Retention Work in Construction Contracts?How retention works and how to get it released on time.
Free templates
- Construction Final Account TemplateContract sum to balance due, submitted against agreed.Free · Excel and PDF
- Construction CVR TemplateMonthly cost and value by package with margin and forecast.Free · Excel and PDF
- Bill of Quantities TemplateItems by NRM2 section with automatic totals.Free · Excel and PDF
Need support with quantity surveying on your project?




