How to Prepare an Interim Payment Application in Construction

An interim application is the start of every payment cycle. Here is what to include, when to submit it and how the Construction Act protects you.

Matthews & Roberts2 min read
Construction site where interim payment applications are valued
On this page
  1. What to include
  2. Timing
  3. The Construction Act payment cycle
  4. Common reasons for underpayment
  5. Applications support across the North West
  6. Free template

An interim payment application sets out the value of work done to date, less what has already been paid. Submitted on time and supported by evidence, it is the strongest tool a contractor or subcontractor has for protecting cash flow.

What to include

  • Measured work valued against the contract sum analysis, activity schedule or bill of quantities
  • Materials on site plus materials off site where the contract allows it
  • Variations or compensation events, agreed and pending, each with a build up
  • Loss and expense where entitlement exists
  • Deductions for retention and previous payments
  • Supporting evidence such as progress photos, measurements and delivery notes

Timing

Contracts set the application date, the due date and the final date for payment. Put every date for the whole project in a calendar at the start. Late applications are often paid a month late.

The Construction Act payment cycle

The Housing Grants, Construction and Regeneration Act 1996, as amended, sets the framework:

  1. 1Payment notice: the payer must issue a payment notice within five days of the due date stating the sum it considers due
  2. 2Pay Less notice: if it intends to pay less than the notified sum, it must issue a Pay Less notice before the prescribed period ahead of the final date for payment
  3. 3Default: if no valid notice is issued, the sum in a valid application can become the notified sum
  4. 4Remedies: the payee can suspend after seven days notice or refer the dispute to adjudication

Read our detailed guide to payment and Pay Less notices.

Common reasons for underpayment

  • Application submitted late or to the wrong person
  • Progress overstated without evidence
  • Variations included without notice or build up
  • Materials claimed that the contract does not allow
  • Retention calculated incorrectly. See retention in construction contracts.

Applications support across the North West

Matthews & Roberts prepares applications for payment for contractors and subcontractors in Liverpool, Manchester, Bolton, the Wirral and across the North West.

Free template

Download our free payment and Pay Less notice templates in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.

Need support on site? Matthews & Roberts provides quantity surveying across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

When should I submit an interim application?

On or before the date set by the contract. Many contracts fix monthly valuation or application dates. Missing the date can push payment back a full cycle.

What is the final date for payment?

The latest date by which the payer must pay the notified sum. The contract sets it, or the Scheme for Construction Contracts applies if the contract does not.

Can I suspend work if I am not paid?

Under the Construction Act a payee can suspend performance for non payment of a notified sum after giving at least seven days written notice of intention to suspend.

Commercial control

Related guides and templates

Each application relies on measured work, variations and notices. These support it.

Need support with quantity surveying on your project?

More insights

View all insights