What Are Daywork Sheets and When Can You Use Daywork in Construction?

Daywork pays for work that cannot be measured, but only if the records are right. Here is when daywork applies and how to complete daywork sheets properly.

Matthews & Roberts2 min read
Construction team recording daywork on a project
On this page
  1. When daywork applies
  2. Rates and definitions
  3. What a good daywork sheet includes
  4. Common mistakes
  5. Daywork and the final account
  6. Commercial support in the North West
  7. Free template

Daywork values work by the actual labour, plant and materials used rather than by measurement. It is a fallback for work that cannot sensibly be measured, such as dealing with unexpected obstructions. It only works if the records are complete and verified at the time.

When daywork applies

Most contracts allow daywork only where varied work cannot properly be valued by measurement or rates. Some require the contract administrator to instruct daywork in advance. Check the contract before assuming daywork is available.

Rates and definitions

The contract sets the basis. Building contracts often refer to the RICS definition of prime cost of daywork, with percentage additions for overheads and profit stated in the tender. Civil engineering contracts often use the CECA dayworks schedule.

What a good daywork sheet includes

  • Date and exact location
  • Instruction or event reference
  • Clear description of the work done
  • Each operative by name, trade and hours
  • Plant by type and hours, including standing time where allowed
  • Materials with quantities and delivery references
  • Signature of the contractor and verification by the other party

Common mistakes

  1. 1Sheets submitted days later when nobody can verify them
  2. 2Vague descriptions such as "assisting" or "clearing up"
  3. 3Daywork used for work that could be measured
  4. 4Signatures obtained "for record only" without agreement of the hours

Daywork and the final account

Unsigned or late daywork sheets are a common cause of disputes in the final account. Getting them right on the day saves arguments months later. See also how variations are valued.

Commercial support in the North West

Matthews & Roberts provides quantity surveyors who set up daywork and change processes for contractors in St Helens, Stockport, Widnes and Runcorn and across the North West.

Free template

Download our free daywork sheet template in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.

Need support on site? Matthews & Roberts provides quantity surveying across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

When can daywork be used?

Daywork is normally used only where varied work cannot properly be valued by measurement. It is often only allowed where the contract administrator has instructed or accepted it.

What should a daywork sheet include?

The date, location, instruction reference, description of the work, names and hours of each operative, plant used with hours and materials with quantities, signed by the contractor and verified by the other party.

What rates apply to daywork?

The contract sets the basis. Building contracts often refer to the RICS definition of prime cost of daywork with agreed percentage additions. Civil engineering contracts often use the CECA dayworks schedule.

Commercial control

Related guides and templates

A commercial review draws on more than one record. These guides and templates support it.

Need support with quantity surveying on your project?

More insights

View all insights