Programme Recovery on Construction Projects: A Practical Approach for North West Contractors

When a project falls behind, the first job is to understand the real position. This guide sets out a practical approach to programme recovery for contractors in Liverpool, Manchester and across the North West.

Matthews & Roberts2 min read
Project team reviewing a construction recovery programme
On this page
  1. 1. Establish the true position
  2. 2. Find the real critical path
  3. 3. Look at the options
  4. 4. Agree the plan and the contract position
  5. 5. Report honestly and often
  6. When to bring in support

Most projects that fall behind do so gradually. By the time the delay is obvious, the team is often too close to the problem to see the way out. A structured recovery gives everyone a clear, realistic plan to work to.

1. Establish the true position

  • Walk the site and record actual progress package by package
  • Update the programme with real progress, not planned progress
  • Identify outstanding design information and approvals
  • Review subcontractor resources and performance
  • Understand the commercial position, including unpriced change

2. Find the real critical path

With a properly updated programme, identify the activities driving completion. These are where recovery effort makes a difference. Effort spent elsewhere rarely changes the end date.

3. Look at the options

  • Resequencing. Can activities run in parallel or in a different order?
  • Resources. Can extra labour or plant be applied to critical work without trades getting in each other's way?
  • Working hours. Are extended hours or weekend working possible and permitted?
  • Design and procurement. Can information or long lead items be accelerated?
  • Scope and phasing. Could the client accept a phased handover?

4. Agree the plan and the contract position

A recovery programme should be realistic, resourced and agreed with the team. Make sure the contract position is protected at the same time: notices of delay, early warnings and compensation events where the cause is not the contractor's risk. See our guides to NEC4 compensation events and JCT extensions of time.

5. Report honestly and often

Weekly reporting against the recovery programme, with clear actions and owners, keeps the client informed and the team focused. Early, honest reporting builds the trust that a recovery depends on.

When to bring in support

An experienced interim project manager can take ownership of a recovery, bring an objective view and free the existing team to focus on delivery.

For an example of programme control across many sites, see the Northern Rail platform validator programme.

Related reading: what a construction project manager does and North West project management case studies. Contact us if a project needs recovering.

Matthews & Roberts provides construction project management and planning and programme support to contractors across Liverpool, Manchester and the North West.

Need hands on help? See our construction programme recovery service or download the free JCT extension of time notice template. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What is the first step in recovering a delayed construction project?

Establish the true position: actual progress against the programme, the real critical path, outstanding information and the commercial position. Every recovery decision relies on that baseline.

Should a recovery programme be submitted to the client?

Usually yes, in line with the contract. Under NEC4 a revised programme is submitted under clause 31. Under JCT, notices and programme updates support any extension of time.

Contract administration

Related guides and templates

Notices, programme and change all affect each other. These cover the related steps.