NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and Recovering

Compensation events are how a contractor recovers time and money under NEC4. This guide explains the events, the eight week time bar, quotations and assessment, with practical steps for project managers on North West sites.

Matthews & Roberts3 min read
NEC4 compensation event records reviewed by a contractor project manager
On this page
  1. What counts as a compensation event
  2. The eight week time bar
  3. Quotations
  4. When the Project Manager does not respond
  5. How a project manager keeps compensation events under control
  6. Free template

Compensation events are the mechanism NEC4 uses to give a contractor more time and money when something happens that is not the contractor's risk. They only work if the process is followed. Time limits are strict. Missing them can turn a valid entitlement into a loss.

Clause references below are to the NEC4 Engineering and Construction Contract. Always check the Contract Data and any Z clauses in your own contract.

What counts as a compensation event

Most compensation events are listed in clause 60.1. Common examples include:

  • The Project Manager instructing a change to the Scope
  • The Client not providing access to the site by the date required
  • The Project Manager or Supervisor not replying within the period the contract requires
  • Physical conditions an experienced contractor would have judged to have a small chance of occurring
  • Weather measured as exceeding the one in ten year conditions set in the Contract Data
  • Work being stopped or not allowed to start by the Project Manager

Additional events can be added through the Contract Data or secondary options.

The eight week time bar

Clause 61.3 requires the Contractor to notify a compensation event within eight weeks of becoming aware of it. If it does not, it is not entitled to a change in the Prices, Completion Date or Key Date, unless the event arises from something the Project Manager should have notified, such as an instruction.

On site, that means:

  • Every instruction, late reply or unexpected condition is logged on the day it happens
  • Someone owns the review of that log every week
  • Notifications go out early rather than waiting for the full cost to be known

Quotations

When the Project Manager instructs a quotation, clause 62.3 gives the Contractor three weeks to submit it. The quotation sets out the proposed changes to the Prices and any delay to Completion or Key Dates, assessed against the Accepted Programme. The Project Manager then has two weeks to reply.

A strong quotation:

  • Uses a current Accepted Programme to show the effect on Completion
  • Builds the cost from Defined Cost using the Schedule of Cost Components
  • Includes the risk allowances an experienced contractor would make
  • Is clear enough for the Project Manager to accept without long rounds of questions

When the Project Manager does not respond

NEC4 includes deemed acceptance provisions. If the Project Manager fails to reply to a notification or quotation within the required time, the Contractor can notify that failure. If the Project Manager still does not reply within two weeks, the notification or quotation is treated as accepted under clause 61.4 or clause 62.6. Track these dates as carefully as your own.

How a project manager keeps compensation events under control

  • A live register of every potential event, notification, quotation and outcome
  • Early warnings raised under clause 15 as soon as a risk appears
  • A programme revised and resubmitted under clause 31 so assessments have a current baseline
  • Defined Cost records kept as the work happens, not reconstructed later

Related reading: NEC4 early warnings and the Accepted Programme under clause 31.

Matthews & Roberts provides NEC4 contract administration for contractors and construction project management across Liverpool, Manchester and the North West. This guide is general information, not legal advice.

Free template

Download our free NEC4 compensation event notification template in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.

Need support on site? Matthews & Roberts provides NEC4 contract administration across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What is a compensation event under NEC4?

A compensation event is an event listed in the contract, mainly in clause 60.1 of the NEC4 Engineering and Construction Contract, that entitles the Contractor to a change in the Prices, the Completion Date or a Key Date if it affects them.

How long does a contractor have to notify a compensation event?

Under clause 61.3 the Contractor must notify within eight weeks of becoming aware that the event has happened. If it does not, it loses the right to a change unless the event is one the Project Manager should have notified.

How long does the Contractor have to submit a quotation?

Under clause 62.3 the Contractor submits a quotation within three weeks of being instructed to do so. The Project Manager replies within two weeks of receiving it, unless a longer period is agreed.

Contract administration

Related guides and templates

Compensation events start with an early warning and end in the valuation. These cover both.