Key facts
- Location
- Northern rail network, North of England
- Our role
- Programme and Project Management
- Sector
- Transport & Highways
- Status
- Complete
- Dates
- 2020 to 2021
Overview
The Platform Validator Programme rolled out new platform validators across 96 operational stations on the Northern rail network. The programme covered engineering, procurement, design, construction and phased commissioning within live transport environments.
Programme and Project Management Scope
Surveys and design
Station by station surveys and impact assessments, translating site constraints, operational requirements and technical interfaces into coordinated design and delivery plans.
Rollout programme
Management of the master rollout programme, work sequencing, site logistics and contingency planning around passenger footfall peaks, station access, possessions and operational constraints.
Stakeholders and supply chain
Coordination of train operating company stakeholders, station operations, designers, suppliers and contractors, including subcontractor performance, procurement, package costs, risk, change and reporting.
Commissioning and handover
Installation readiness, testing, phased commissioning, transition into use and handover governance, with controlled close out documentation across a geographically dispersed programme.
Approach
With 96 stations and passengers on every platform, consistency was everything. A repeatable process for survey, installation and commissioning was established early and refined as the rollout progressed, keeping disruption to a minimum.
Outcome
Platform validators were installed and commissioned across 96 stations on the Northern network.
Matthews & Roberts provides project management and programme management on rail and transport projects. See our transport and highways work.
Frequently asked questions
How is work planned at live rail stations?
Around passengers and train operations. Station surveys identify constraints, work is scheduled away from peak footfall and coordinated with station staff. Access and possessions are booked well in advance.
What is phased commissioning?
Bringing new equipment into service in stages rather than all at once. Each phase is tested and handed over before the next begins, which limits disruption and lets lessons from early stations improve later ones.
Contract administration
Guides and templates for this kind of work
Notices, programme and change all affect each other. These cover the related steps.
Guides
- NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and RecoveringNotifying and valuing compensation events under clause 60.
- NEC4 Early Warnings: A Contractor's Guide to Clause 15 and the Early Warning RegisterRaising early warnings under clause 15 and running the register.
- NEC4 Accepted Programme: What Clause 31 Requires and Why It Protects the ContractorGetting the programme accepted and keeping it current.