Construction Project Mobilisation: A First 10 Working Days Checklist

What an external project manager should review, set up and report back in the first 10 working days on a contractor's project, written for Liverpool and North West contractors.

Matthews & Roberts2 min read
Construction project management mobilisation on a Liverpool site
On this page
  1. Days 1 to 3: review
  2. Days 3 to 6: walk and meet
  3. Days 6 to 10: set up
  4. Day 10: report back
  5. Why it matters
  6. Free template

In the first 10 working days an external project manager should establish the true position on the project, put the core controls in place and give the contractor a clear report on where things stand. This checklist sets out what that looks like in practice.

Days 1 to 3: review

  • The contract, amendments, scope and key dates
  • The programme against actual progress on site
  • The subcontract and procurement position, including packages still to let
  • Design information released and still outstanding
  • The risk register, early warnings, notices and open change
  • The Construction Phase Plan, temporary works register and site rules
  • Client requirements, reporting expectations and key stakeholders

Days 3 to 6: walk and meet

  • Walk the whole site with the site manager
  • Meet each subcontractor's supervisor
  • Meet the design team and the client's representative
  • Agree the meeting structure: progress, design, commercial and safety
  • Confirm who holds which authority for instructions and orders

Days 6 to 10: set up

  • An updated programme with real progress and a three week look ahead
  • A live risk and opportunity register
  • An information required schedule tied to the programme
  • A change and notice register for NEC or JCT procedures
  • A simple weekly reporting format for the client and the business

Day 10: report back

The contractor should receive a short mobilisation report covering:

  1. 1The true programme position and the critical path
  2. 2The commercial position, including unpriced change
  3. 3The top five risks and how they will be managed
  4. 4Information and decisions needed, with dates
  5. 5An action plan with owners

Why it matters

A clear baseline in the first fortnight prevents months of guesswork later. It also gives the contractor's management an honest view of the project before small issues grow.

Related reading: bringing in an external project manager, programme recovery and NEC4 compensation events.

See how mobilisation and reporting were set up on the NHS modular CT scanner facility.

Related reading: how to choose a project management company in Liverpool and what to expect from a project management company in Manchester.

Matthews & Roberts provides construction project management in Liverpool and across the North West, including interim project managers who can mobilise quickly.

Free template

Download our free construction mobilisation checklist in Word, Excel or PDF. It is white labelled, so you can add your own company details. Browse all our free construction templates.

Need support on site? Matthews & Roberts provides pre construction project management across Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What should a project manager do in the first week on a project?

Establish the true position: review the contract, programme, subcontract position, design information and risks, walk the site and meet the team. Every decision after that relies on this baseline.

What should the contractor get back after the first 10 days?

A short mobilisation report: the current programme and cost position, the top risks and open issues, the information still needed and a clear action plan with owners and dates.

Project set up and delivery

Related guides and templates

Good projects are set up early. These cover the steps either side of this one.

Need support with project management on your project?

More insights

View all insights