A baseline programme is the agreed plan for building the job, set at the start and used as the reference for measuring progress, forecasting completion and assessing the effect of change. Get it right and every later decision has a solid reference point.
Tender programme or baseline programme?
| Tender programme | Baseline programme | |
|---|---|---|
| Purpose | Show the client a credible approach | Plan and control the actual work |
| Detail | Key activities and dates | Full logic, resources and procurement |
| Built with | Bid and estimating team | Delivery team and subcontractors |
| Used for | Winning the work | Progress, change and delay |
Purpose
- Tender programme
- Show the client a credible approach
- Baseline programme
- Plan and control the actual work
Detail
- Tender programme
- Key activities and dates
- Baseline programme
- Full logic, resources and procurement
Built with
- Tender programme
- Bid and estimating team
- Baseline programme
- Delivery team and subcontractors
Used for
- Tender programme
- Winning the work
- Baseline programme
- Progress, change and delay
Our tender programme service covers the first. This guide covers the second.
What a good baseline programme includes
- 1Logic. Every activity linked so the critical path is real.
- 2Procurement and design. Long lead items and information release dates shown where they drive the work.
- 3Key dates. Access dates, sectional completions and client milestones.
- 4Realistic durations. Based on outputs your teams and subcontractors can actually achieve.
- 5Float and risk. Shown openly rather than hidden in durations.
Keeping it useful
A baseline is only useful if progress is measured against it honestly. Update progress weekly, keep a short term look ahead and record the reasons for any slippage. Under NEC4, submit revised programmes when the contract requires them. See our guide to the NEC4 Accepted Programme.
When the job slips, the baseline is what shows how far and why. Our guide to programme recovery explains the next steps.
Construction planners across the North West
Matthews & Roberts provides construction planners for contractors and clients in Liverpool, Manchester, Chester, Warrington, Preston and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.
Frequently asked questions
What is a baseline programme in construction?
The agreed construction programme at the start of the job, used as the reference for measuring progress and assessing the effect of change.
Is a baseline programme the same as the Accepted Programme under NEC4?
Not exactly. The first Accepted Programme often acts as the baseline, but under NEC4 the Accepted Programme is replaced each time a revised programme is accepted.
Who prepares the baseline programme?
Usually the contractor's planner, built with the project manager, site team and key subcontractors.
Contract administration
Related guides and templates
Notices, programme and change all affect each other. These cover the related steps.
Guides
- NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and RecoveringNotifying and valuing compensation events under clause 60.
- Programme Recovery on Construction Projects: A Practical Approach for North West ContractorsBuilding a credible recovery programme when the job slips.
- How Are Construction Variations Valued? A Guide for ContractorsValuing change under the contract so it lands in the CVR.
- How to Prepare an Interim Payment Application in ConstructionBuilding an application that is easy to agree and quick to pay.
Free templates
- Weekly Progress Report TemplateSafety, programme, look ahead, RFIs and risks each week.Free · Word and PDF
- NEC4 Early Warning Register TemplateLog, review and close early warnings at each meeting.Free · Excel and PDF
- NEC4 Compensation Event Notification TemplateNotify a compensation event within the time bar.Free · Word and PDF