What Is a Construction Baseline Programme? A Contractor's Guide

The baseline programme is the plan everything else is measured against. Here is what it should contain and how to keep it working.

Matthews & Roberts1 min read
Construction baseline programme reviewed by a planner
On this page
  1. Tender programme or baseline programme?
  2. What a good baseline programme includes
  3. Keeping it useful
  4. Construction planners across the North West

A baseline programme is the agreed plan for building the job, set at the start and used as the reference for measuring progress, forecasting completion and assessing the effect of change. Get it right and every later decision has a solid reference point.

Tender programme or baseline programme?

Purpose

Tender programme
Show the client a credible approach
Baseline programme
Plan and control the actual work

Detail

Tender programme
Key activities and dates
Baseline programme
Full logic, resources and procurement

Built with

Tender programme
Bid and estimating team
Baseline programme
Delivery team and subcontractors

Used for

Tender programme
Winning the work
Baseline programme
Progress, change and delay

Our tender programme service covers the first. This guide covers the second.

What a good baseline programme includes

  1. 1Logic. Every activity linked so the critical path is real.
  2. 2Procurement and design. Long lead items and information release dates shown where they drive the work.
  3. 3Key dates. Access dates, sectional completions and client milestones.
  4. 4Realistic durations. Based on outputs your teams and subcontractors can actually achieve.
  5. 5Float and risk. Shown openly rather than hidden in durations.

Keeping it useful

A baseline is only useful if progress is measured against it honestly. Update progress weekly, keep a short term look ahead and record the reasons for any slippage. Under NEC4, submit revised programmes when the contract requires them. See our guide to the NEC4 Accepted Programme.

When the job slips, the baseline is what shows how far and why. Our guide to programme recovery explains the next steps.

Construction planners across the North West

Matthews & Roberts provides construction planners for contractors and clients in Liverpool, Manchester, Chester, Warrington, Preston and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What is a baseline programme in construction?

The agreed construction programme at the start of the job, used as the reference for measuring progress and assessing the effect of change.

Is a baseline programme the same as the Accepted Programme under NEC4?

Not exactly. The first Accepted Programme often acts as the baseline, but under NEC4 the Accepted Programme is replaced each time a revised programme is accepted.

Who prepares the baseline programme?

Usually the contractor's planner, built with the project manager, site team and key subcontractors.

Contract administration

Related guides and templates

Notices, programme and change all affect each other. These cover the related steps.

Need support with programme management on your project?

More insights

View all insights