Construction Project Mobilisation Checklist

A free checklist that takes a project from contract award to the first weeks on site, covering the contract, programme, CDM, site set up and supply chain.

Free to download, no sign up. White labelled so you can add your own company name and logo.

Need help using it?0151 332 6581info@matthewsroberts.com

Preview of the Construction mobilisation checklist

About this template

What the Construction mobilisation checklist is for

The first few weeks decide how a project runs. A missed licence, a late long lead order or a programme nobody agreed can cost months later.

This checklist brings together what a project manager needs to have in place between contract award and the first weeks on site.

What is included

  • Contract and commercial checks
  • Programme and long lead items
  • CDM 2015 and safety
  • Site set up, utilities and licences
  • Team and supply chain
  • Sign off

How to use it

Using the Construction mobilisation checklist on your project

  1. 01

    Start at award

    Open the checklist as soon as the contract is awarded.

  2. 02

    Assign owners

    Give every item an owner and a target date.

  3. 03

    Review weekly

    Review progress at the mobilisation meeting.

  4. 04

    Sign off

    Close the checklist once the site is running to plan.

Avoid these

Common mistakes we see on site

  • Starting on site before the Construction Phase Plan is in place
  • Long lead items ordered late
  • Highway licences applied for too late
  • No agreed reporting rhythm with the client

Prefer us to handle it?

We can run this for you on site

Matthews & Roberts provides the people behind these templates: Temporary Works Coordinators, quantity surveyors, project managers and health and safety consultants across Liverpool, Manchester, the North West and North Wales.

Send us a message
Insights
View all insights

FAQ

Construction Project Mobilisation Checklist: questions

What does mobilisation mean in construction?

The period between contract award and full production on site, when the team, programme, documents, site set up and supply chain are put in place.

How long does mobilisation take?

It depends on the project, but planning should start as soon as the contract is awarded.

Can you help us mobilise a new project?

Yes. Our pre construction project managers mobilise projects for contractors across the North West and North Wales.

Talk to us

Need support on your project?

Tell us about your site and what you need. We will come back within one working day with a clear proposal and a named consultant.

Call 0151 332 6581

Email info@matthewsroberts.com

3a Bridgwater Street, Baltic Triangle, Liverpool L1 0AR

Send us a message

Or call 0151 332 6581 or email info@matthewsroberts.com

We use your details only to reply to your enquiry.