The first week on a new site sets the standard for everything that follows. Under CDM 2015 the Principal Contractor must plan, manage, monitor and coordinate the construction phase. Most of that planning needs to be complete before the first operative arrives.
Use this checklist to confirm the essentials are in place.
Before work starts
- Written appointment as Principal Contractor received from the client
- Preconstruction information reviewed and gaps raised with the client and Principal Designer
- Construction Phase Plan drawn up and specific to the project
- F10 notification displayed on site where the project is notifiable
- Welfare facilities to Schedule 2 in place and working
- Site boundary secure with measures to prevent unauthorised access
- Traffic routes, pedestrian routes and delivery arrangements set out
- Emergency procedures, first aid and fire arrangements agreed
- Temporary Works Coordinator appointed where temporary works are planned
During the first week
- Every worker inducted before starting work, with records kept
- Site rules issued and displayed
- RAMS for each starting package reviewed against the work planned
- Permit to work arrangements live for high risk activities
- First coordination meeting held with every contractor on site
- Arrangements in place to consult and engage with workers
- First inspection completed with actions recorded and assigned
Keeping it going
- Construction Phase Plan reviewed as the sequence and subcontractors change
- Inspections and audits scheduled with actions tracked to close
- Information for the Health and Safety File gathered as work progresses
- Regular liaison with the Principal Designer on design changes and residual risks
For the full explanation of the duties, read our guide to Principal Contractor duties under CDM 2015 and our guide to the Construction Phase Plan. If temporary works are planned, use our TWC appointment checklist.
Matthews & Roberts provides Principal Contractor support and construction health and safety consultants to contractors across Liverpool, Manchester, Chester and the North West. Get in touch before your next site starts.
Frequently asked questions
Must the Construction Phase Plan be in place before work starts?
Yes. Under CDM 2015 the Principal Contractor must draw up the Construction Phase Plan before the construction phase begins and the client must make sure it is in place before work starts.
What welfare must be provided from day one?
Schedule 2 of CDM 2015 sets the minimum: sanitary conveniences, washing facilities, drinking water, changing rooms, lockers and facilities for rest. They should be available from the start of the construction phase.
Can Matthews & Roberts help set up a new site?
Yes. We support Principal Contractors across the North West with Construction Phase Plans, site rules, inductions, RAMS review and inspections from mobilisation onwards.
CDM and site safety
Related guides and templates
CDM duties connect from planning to handover. These cover the related documents and checks.
Guides
- CDM 2015 Explained: What the CDM Regulations Mean for ContractorsThe Construction (Design and Management) Regulations 2015 apply to every construction project in Great Britain. This...
- Construction Site Health and Safety Inspections: What Should Be Checked?Site inspections are how contractors find out whether their health and safety arrangements are working. This guide...
- RAMS Review: Who Reviews Subcontractor RAMS and What Should They Check?Reviewing subcontractor RAMS is one of the main ways a Principal Contractor controls the construction phase. This...
- RAMS in Construction: Risk Assessments and Method Statements That Work on SiteRAMS are the most common health and safety documents on any construction site. This guide explains what RAMS are,...
Free templates
- Construction Project Mobilisation ChecklistEverything to have in place before work starts on site.Free · Word and PDF
- Construction Phase Plan TemplateA CDM 2015 plan ready to make site specific.Free · Word and PDF
- RAMS Template for ConstructionTask sequence, risks, controls and briefing record.Free · Word and PDF