The Appointment
This was a client side project management appointment. The role represented the NHS client's interests through the delivery of a new modular CT scanner facility and its enabling infrastructure, within a live and occupied hospital estate. Clinical services continued around the site throughout.
The Client's Brief
The client needed new diagnostic capacity delivered without disrupting patients, staff or clinical operations. The facility had to integrate with the existing estate and its infrastructure, meet accessibility and fire safety requirements and be commissioned ready for safe operational use.
Role and Reporting
The client side project manager worked on behalf of the client and coordinated NHS estates and operational stakeholders, clinical users, design consultants, specialist suppliers and contractors. Progress, risk, change and budget forecasts were reported back to the client so decisions were made with a clear view of the position.
Work Undertaken
Scope and design coordination
Definition of the scope and coordination of design to align technical, accessibility, operational and programme requirements.
Programme, budget and procurement
Management of programme, budget forecasting, procurement, risk, change and reporting.
Safety and CDM
Oversight of safety and CDM compliance, including accessibility and DDA reviews, fire and life safety interfaces, operational impact assessments, emergency response planning and coordination of site wide evacuation procedures.
Commissioning and handover
Governance of quality, testing, commissioning, change control and document control through to safe operational use.
Interfaces Managed
- The modular facility and the existing hospital estate
- Enabling infrastructure and supporting services
- Clinical operations continuing around the works
- Emergency routes and evacuation procedures across the site
The Delivery Challenge
In a live hospital, service continuity comes first. Every activity was assessed for its impact on patients, staff and visitors, agreed with estates and clinical teams in advance and controlled through clear procedures on site.
Outcome
The new CT scanner facility was commissioned and handed over for operational use, adding diagnostic capacity to the hospital.
Commissioning work on an occupied or operational building? See our client side construction project management service for estates teams, developers and organisations commissioning construction and refurbishment work across Liverpool and the North West. We also provide CDM advisory services and work across the education and public sector.
Frequently asked questions
What is client side project management?
It is project management carried out on behalf of the organisation commissioning the work. The client side project manager coordinates consultants and contractors, oversees programme, cost and risk and reports back to the client so decisions are made with a clear view of the position.
Why are modular buildings used for diagnostic facilities?
Modular units are largely built off site, so time on a busy hospital site is short. This reduces disruption to patients and staff and brings new diagnostic capacity into use sooner.
What matters most when building within a live hospital?
Protecting patients, staff and visitors. Fire and life safety interfaces, accessibility, emergency routes and service continuity must be planned in detail and agreed with estates and clinical teams before work starts.
Contract administration
Guides and templates for this kind of work
Notices, programme and change all affect each other. These cover the related steps.
Guides
- NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and RecoveringNotifying and valuing compensation events under clause 60.
- NEC4 Early Warnings: A Contractor's Guide to Clause 15 and the Early Warning RegisterRaising early warnings under clause 15 and running the register.
- NEC4 Accepted Programme: What Clause 31 Requires and Why It Protects the ContractorGetting the programme accepted and keeping it current.