Inspection and Test Plans (ITPs) in Construction Explained

An ITP turns the specification into a practical checklist for site. Here is how they work.

Matthews & Roberts1 min read
Engineer completing an inspection and test plan on site
On this page
  1. What an ITP includes
  2. Hold and witness points
  3. Making ITPs work
  4. Quality assurance support

An inspection and test plan (ITP) sets out every inspection and test for a package of work: what is checked, when, against which standard, by whom and what record is produced. It turns the specification into a practical checklist the site team can follow.

What an ITP includes

Activity

Purpose
The stage of work, in sequence

Check or test

Purpose
What is inspected or tested

Acceptance criteria

Purpose
The standard or tolerance to meet

Frequency

Purpose
How often the check is made

Responsibility

Purpose
Who carries it out

Hold or witness

Purpose
Whether work must stop or the client may attend

Record

Purpose
The certificate, form or photo produced

Hold and witness points

A hold point stops work until the inspection is done and the work is released. Use them before work is covered up, such as reinforcement before a pour. A witness point invites the client to attend but does not stop work if they do not.

Making ITPs work

  • Prepare them before work starts and agree them with the client
  • Keep them short and specific to the package
  • Collect records as you go, not at handover
  • Link non conformances to corrective action and close out

Quality assurance support

Our inspection and test plan service prepares ITPs and manages inspections. See also our guide to snagging and handover and our Davyhulme case study. We cover Liverpool, Manchester and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What is an ITP in construction?

An inspection and test plan lists the inspections and tests for a package of work, the acceptance criteria, who carries them out and the records produced.

What is the difference between a hold point and a witness point?

At a hold point work must stop until the inspection is done and the work released. At a witness point the client is invited to attend, but work can continue if they do not.

Who signs an ITP?

The person carrying out each check, with sign off by the contractor and, at hold and witness points, the client or their representative.

Project set up and delivery

Related guides and templates

Good projects are set up early. These cover the steps either side of this one.

Need support with quality assurance on your project?

More insights

View all insights