A good handover is planned from the start: records collected as work progresses, snags tracked to close out with clear owners and the client trained and ready to occupy. Leaving it to the last month almost always delays completion.
A simple handover plan
- 1Agree what complete means. Practical completion criteria, documents and training.
- 2Collect records as you go. Certificates and test results with each package.
- 3Snag early and often. Area by area, not one huge list at the end.
- 4Track to close out. Every snag has an owner, a date and a check.
- 5Hand over in an orderly way. Documents, keys, training and the Health and Safety File.
Snag list essentials
| Field | Why it matters |
|---|---|
| Location | So the trade can find it |
| Description and photo | So the fix is clear |
| Responsible trade | So someone owns it |
| Target date | So progress can be tracked |
| Closed and checked | So it does not reappear |
Location
- Why it matters
- So the trade can find it
Description and photo
- Why it matters
- So the fix is clear
Responsible trade
- Why it matters
- So someone owns it
Target date
- Why it matters
- So progress can be tracked
Closed and checked
- Why it matters
- So it does not reappear
Common causes of messy handovers
- Certificates chased after completion
- Snag lists with no owners
- Commissioning squeezed at the end
- O&M information that does not match what was installed
Support with snagging and handover
Our snagging and handover service works for contractors and clients. See also inspection and test plans and commissioning assurance. We cover Liverpool, Manchester and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.
Frequently asked questions
When should handover planning start?
At the start of the project. Records, certificates and O&M information are far easier to collect as work progresses.
What is the difference between snagging and defects?
Snagging usually refers to minor defects or incomplete items found before handover. Defects found after practical completion are dealt with under the contract's defects provisions.
What records are needed at handover?
Test and commissioning certificates, building control completion, O&M manuals, the Health and Safety File and any warranties.
Project set up and delivery
Related guides and templates
Good projects are set up early. These cover the steps either side of this one.
Guides
- Construction Project Mobilisation: A First 10 Working Days ChecklistWhat an external project manager should review, set up and report back in the first 10 working days on a...
- What Should a Construction Project Management Proposal Include?Comparing project management proposals? Use this checklist to see what each one really offers.
- How Much Does Construction Project Management Cost?There is no single price for construction project management. Here is how fees are usually structured and what...
- Can You Hire a Construction Project Manager Two Days a Week?Not every project needs a full time project manager. Here is when part time support works and how to make it effective.
Free templates
- Construction Snagging List TemplateDefects with owners, dates and open and closed counts.Free · Excel and PDF
- Construction Project Mobilisation ChecklistEverything to have in place before work starts on site.Free · Word and PDF
- Request for Information (RFI) TemplateOne clear question, a due date and a register to track it.Free · Word and PDF
Need support with quality assurance on your project?