Key facts
- Location
- South Mosman, Sydney, Australia
- Our role
- Construction Management
- Sector
- Transport & Highways
- Status
- Complete
- Dates
- 2024 to 2025
Overview
South Mosman Wharf is a commuter ferry wharf on Sydney Harbour. The upgrade replaced the former structure with an accessible facility, including a floating pontoon on new piles, a covered gangway and passenger waiting area, a new lift and stairs, glazed screens, CCTV, lighting and improved landside connections.
Construction began in June 2024 and the upgraded wharf reopened to the public in January 2025.
Construction Management Scope
The construction management role covered the coordination of every discipline on a constrained marine site.
Marine civils and structures
Coordination of demolition, marine civils, piling, architectural steelwork and access structures, with sequencing planned around tides, weather and harbour traffic.
Design and fabrication
Review of design and fabricator submissions, tolerance checks, off site manufacture and factory inspections so components arrived ready to install.
High risk lifting and marine methods
Planning of high risk lifts and marine method workshops with the delivery team before work began on the water.
MEP interfaces
Coordination of lift, lighting, CCTV and electrical services with the structural and architectural packages.
Safety, progress and commercial reporting
Site safety management, progress reporting and commercial reporting to the client throughout delivery.
Approach
Marine work leaves little room for error. Components were inspected before they left the factory, lifts were planned in detail before plant was mobilised and the sequence of works was built around the conditions on the harbour. Junior engineers and site staff were mentored throughout so standards stayed consistent across every shift.
Outcome
The upgraded South Mosman Wharf reopened to the public in January 2025 with step free access, a new floating pontoon and improved passenger facilities.
Matthews & Roberts provides project management and quality assurance on complex transport and infrastructure projects. See our transport and highways work.
Frequently asked questions
What does project management involve on a marine wharf upgrade?
It covers sequencing marine civils, piling, pontoon and gangway installation around tides and weather, coordinating off site fabrication and factory inspections, planning high risk lifts from the water and managing interfaces with the operating ferry network.
Why are accessibility upgrades common on ferry wharves?
Older wharves often lack step free access. Upgrades typically add floating pontoons that move with the tide, covered gangways, lifts and improved landside connections so every passenger can board safely.
Contract administration
Guides and templates for this kind of work
Notices, programme and change all affect each other. These cover the related steps.
Guides
- NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and RecoveringNotifying and valuing compensation events under clause 60.
- NEC4 Early Warnings: A Contractor's Guide to Clause 15 and the Early Warning RegisterRaising early warnings under clause 15 and running the register.
- NEC4 Accepted Programme: What Clause 31 Requires and Why It Protects the ContractorGetting the programme accepted and keeping it current.




