Key facts
- Location
- York, Yorkshire
- Our role
- Project Management
- Sector
- Transport & Highways
- Status
- Complete
- Dates
- 2019 to 2021
On this page
Overview
The project delivered a new first class passenger lounge for LNER at York railway station. The works included building works and fit out within a live, heritage sensitive station, with excavation, structural footings and associated civil and temporary works interfaces.
Project Management Scope
Stakeholder coordination
Coordination of client stakeholders, architects, engineering consultants, contractors and station operations, with active oversight of safety and CDM compliance.
Design and approvals
Management of design development, technical submissions, document control and approvals with architects and conservation stakeholders, balancing operational requirements, accessibility, buildability, heritage constraints and design intent.
Programme, cost and logistics
Control of programme, budget, risk, change, procurement, subcontract package performance and site logistics, with detailed planning around access, passenger interfaces and continuity of operations.
Archaeological discovery
During footing excavation an unexpected archaeological discovery paused the works. The project response was coordinated with archaeological and statutory bodies, the works were resequenced and programme and risk impacts were managed before work resumed safely.
Quality and handover
Quality assurance, testing, defects, as built and handover information and operational readiness through to completion.
Approach
A working station leaves no margin for disruption. Every activity was planned around passengers and station operations. When the unexpected happened the response was calm, compliant and coordinated with every party involved.
Outcome
The new first class lounge was completed and handed over at York station.
Matthews & Roberts provides project management and temporary works support on rail and heritage projects. See our transport and highways work.
Frequently asked questions
What are the challenges of building inside a heritage railway station?
The building must stay open to passengers, works must respect the listed fabric and design intent. Conservation stakeholders also need to approve the proposals. Access, noise, dust and safety all need careful control.
What happens if archaeology is found during excavation?
Work in the affected area stops, the find is reported and specialists and the relevant authorities are brought in. Once their requirements are met the works are resequenced so the project can resume safely.
Contract administration
Guides and templates for this kind of work
Notices, programme and change all affect each other. These cover the related steps.
Guides
- NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and RecoveringNotifying and valuing compensation events under clause 60.
- NEC4 Early Warnings: A Contractor's Guide to Clause 15 and the Early Warning RegisterRaising early warnings under clause 15 and running the register.
- NEC4 Accepted Programme: What Clause 31 Requires and Why It Protects the ContractorGetting the programme accepted and keeping it current.




