Key facts
- Location
- United Kingdom
- Our role
- Programme Management
- Sector
- Housing & Residential
- Status
- Complete
- Dates
- 2021 to 2023
Overview
The programme brought four residential developments forward at the same time, delivering 186 homes and apartments in total:
- 68 affordable homes
- 28 luxury homes
- 16 affordable homes and a 52 unit apartment complex
- 22 speculative homes
Common civils, groundworks, drainage, utilities, access and external works were coordinated across the schemes alongside building delivery.
Programme Management Scope
Portfolio governance
A master programme, stage gates, reporting, document control and dependency management across design, planning, procurement, construction and completion.
Design, planning and procurement
Coordination of consultants and contractors through design development, technical and planning approvals, work package strategy, tendering, procurement and mobilisation.
Temporary works
Temporary Works Coordinator role, managing the temporary works register and coordinating design briefs, design checks, inspections and permits.
Cost and risk
Management of budgets, cash flow and cost forecasting, procurement, change and risk with the commercial teams, with recovery action where a scheme threatened programme objectives.
Delivery and handover
Monitoring of contractor performance, safety and CDM compliance, quality, logistics and sequencing through phased completions, defects, handover and occupation.
Approach
Running four schemes together only works with one source of truth. A single master programme and consistent reporting gave early sight of any scheme drifting from plan, so resources could be moved before a problem affected the wider programme.
Outcome
The programme delivered 186 homes and apartments across four sites, including affordable, luxury and speculative housing.
Matthews & Roberts provides project management, programme management and temporary works support on residential developments. See our housing and residential work.
Frequently asked questions
How are several residential schemes managed at the same time?
Through portfolio governance: one master programme, consistent stage gates and reporting, shared procurement where it makes sense and clear dependency management so that resources move between sites without delaying any of them.
Why appoint a temporary works coordinator on housing schemes?
Excavations, propping, scaffolding and crane bases are common on residential sites. A temporary works coordinator makes sure each item is designed, checked, installed and inspected before it is used.
Contract administration
Guides and templates for this kind of work
Notices, programme and change all affect each other. These cover the related steps.
Guides
- NEC4 Compensation Events: A Contractor's Guide to Notifying, Quoting and RecoveringNotifying and valuing compensation events under clause 60.
- NEC4 Early Warnings: A Contractor's Guide to Clause 15 and the Early Warning RegisterRaising early warnings under clause 15 and running the register.
- NEC4 Accepted Programme: What Clause 31 Requires and Why It Protects the ContractorGetting the programme accepted and keeping it current.