The Health and Safety File: What Goes In It and Who Is Responsible

The Health and Safety File is often rushed at the end of a project. Here is what it should contain and how to build it as you go.

Matthews & Roberts1 min read
Health and Safety File documents being assembled for handover
On this page
  1. What goes in the file
  2. Who does what
  3. How to avoid a last minute scramble
  4. Related guides

The Health and Safety File holds the information someone will need to clean, maintain, alter or demolish the building safely in future. It is not a copy of everything produced on the project. It should not be assembled in a rush at handover.

What goes in the file

Residual hazards and how they are managed

Leave out
Construction phase RAMS

Key structural principles and safe loads

Leave out
Day to day site records

Hazardous materials left in place

Leave out
Routine correspondence

Services and isolation points

Leave out
Information with no future safety value

Safe access for maintenance

Leave out

Who does what

  • Principal Designer: prepares, reviews and updates the file.
  • Principal Contractor: provides information from the construction phase.
  • Designers and contractors: provide information about their work.
  • Client: keeps the file and makes it available for future work.

How to avoid a last minute scramble

Agree what each contractor must provide at the start, collect it as each package finishes and review it before practical completion. Our Principal Contractor support service sets this up from day one.

See Principal Contractor duties and Principal Designer duties.

Matthews & Roberts supports Principal Contractors in Liverpool, Manchester, Chester and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.

Frequently asked questions

What is a Health and Safety File?

A record of information someone will need to clean, maintain, alter or demolish the building safely in future.

Who prepares the Health and Safety File?

The Principal Designer prepares it with information from the Principal Contractor and designers. The client keeps it.

Is the Health and Safety File required on every project?

It is required on projects with more than one contractor.

CDM and site safety

Related guides and templates

CDM duties connect from planning to handover. These cover the related documents and checks.

Need support with principal contractor support on your project?

More insights

View all insights
CDM Advisory

Principal Contractor Duties Under CDM 2015: A Practical Guide

The Principal Contractor controls health and safety during the construction phase of any project with more than one contractor. This guide explains when a Principal Contractor is required, what CDM 2015 says they must do and how those duties translate into day to day site management.

Read insight