On this page
Under CDM 2015, the Principal Designer plans, manages, monitors and coordinates health and safety in the pre construction phase, so foreseeable risks are removed or reduced through design before anyone starts work. The client must appoint one whenever there is, or is likely to be, more than one contractor.
The main duties
| Duty | What it means in practice |
|---|---|
| Plan and coordinate | Design reviews that consider how the building will be built, used, maintained and demolished |
| Manage design risk | Make sure designers eliminate or reduce risks and pass on information about those that remain |
| Pre construction information | Help the client gather and share pre construction information |
| Liaise | Share information with the Principal Contractor for the Construction Phase Plan |
| Health and Safety File | Prepare, review and update the file, then hand it to the client |
Plan and coordinate
- What it means in practice
- Design reviews that consider how the building will be built, used, maintained and demolished
Manage design risk
- What it means in practice
- Make sure designers eliminate or reduce risks and pass on information about those that remain
Pre construction information
- What it means in practice
- Help the client gather and share pre construction information
Liaise
- What it means in practice
- Share information with the Principal Contractor for the Construction Phase Plan
Health and Safety File
- What it means in practice
- Prepare, review and update the file, then hand it to the client
Who can be Principal Designer?
A designer with control over the pre construction phase and the skills, knowledge and experience for the project's risks. On design and build projects the contractor often takes the role. On traditional projects it is usually the lead designer.
Two Principal Designer roles
The Building Safety Act brought a separate Principal Designer role for building regulations compliance. It is not the same as the CDM role, even though the title is identical. Check which role an appointment covers.
Support with the role
Matthews & Roberts provides Principal Designer support where the role and scope are agreed. We advise clients through our CDM client advisor service. We cover Liverpool, Manchester, Chester and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.
This article is general guidance. Refer to CDM 2015 and HSE guidance L153 for the full requirements.
Frequently asked questions
When is a Principal Designer required under CDM 2015?
When there is, or is likely to be, more than one contractor working on the project. The client must appoint the Principal Designer in writing.
Can the Principal Contractor also be the Principal Designer?
Yes, if the organisation has the skills, knowledge and experience for both roles and is appointed to each. This is common on design and build projects.
Is the CDM Principal Designer the same as the Building Safety Act Principal Designer?
No. They are separate roles under different regulations. One organisation can hold both only if it is competent and appointed for each.
CDM and site safety
Related guides and templates
CDM duties connect from planning to handover. These cover the related documents and checks.
Guides
- CDM 2015 Explained: What the CDM Regulations Mean for ContractorsThe Construction (Design and Management) Regulations 2015 apply to every construction project in Great Britain. This...
- The Health and Safety File: What Goes In It and Who Is ResponsibleThe Health and Safety File is often rushed at the end of a project. Here is what it should contain and how to build...
- Principal Contractor Checklist: The First Week on SiteThe first week on site sets the standard for the whole construction phase. This checklist covers what a Principal...
- Construction Site Health and Safety Inspections: What Should Be Checked?Site inspections are how contractors find out whether their health and safety arrangements are working. This guide...
Free templates
- Construction Phase Plan TemplateA CDM 2015 plan ready to make site specific.Free · Word and PDF
- RAMS Template for ConstructionTask sequence, risks, controls and briefing record.Free · Word and PDF
- Construction Health and Safety Audit ChecklistDocuments, site conditions and welfare with an action log.Free · Word and PDF
Need support with cdm advisory on your project?