Pre construction information is the information the client already holds, or can reasonably obtain, that designers and contractors need to plan the work safely. CDM 2015 requires it on every project, in proportion to the risk.
What to include
| Topic | Examples |
|---|---|
| The project | Description, programme, key dates, client requirements |
| The site | Boundaries, access, neighbours, ground conditions |
| Existing structures | Drawings, structural information, previous Health and Safety Files |
| Hazards | Asbestos surveys, services, contamination, confined spaces |
| Use of the site | Occupied areas, live operations, public access |
| Client rules | Permits, security, working hours |
The project
- Examples
- Description, programme, key dates, client requirements
The site
- Examples
- Boundaries, access, neighbours, ground conditions
Existing structures
- Examples
- Drawings, structural information, previous Health and Safety Files
Hazards
- Examples
- Asbestos surveys, services, contamination, confined spaces
Use of the site
- Examples
- Occupied areas, live operations, public access
Client rules
- Examples
- Permits, security, working hours
Common gaps
- No asbestos survey before refurbishment or demolition
- Buried services shown from old records only
- Ground information not shared with temporary works designers
- Occupied building arrangements left to the contractor to discover
How it fits with the other CDM documents
Pre construction information feeds the design, the tender and the Construction Phase Plan. Information about risks that remain at the end goes into the Health and Safety File.
Help with pre construction information
Our pre construction information service gathers and reviews the information and shares it with the right people. We support clients in Liverpool, Manchester, the North West and North Wales. Call 0151 332 6581 or email info@matthewsroberts.com.
Frequently asked questions
Who provides pre construction information?
The client, with help from the Principal Designer where one is appointed.
When should pre construction information be provided?
As early as possible, so designers and contractors can use it when they plan and price the work.
Does every project need pre construction information?
Yes. CDM 2015 requires the client to provide it on every project, in proportion to the risks involved.
CDM and site safety
Related guides and templates
CDM duties connect from planning to handover. These cover the related documents and checks.
Guides
- CDM 2015 Explained: What the CDM Regulations Mean for ContractorsThe Construction (Design and Management) Regulations 2015 apply to every construction project in Great Britain. This...
- Principal Designer Duties Under CDM 2015 ExplainedThe Principal Designer coordinates health and safety through design. Here is what the role involves under CDM 2015.
- The Health and Safety File: What Goes In It and Who Is ResponsibleThe Health and Safety File is often rushed at the end of a project. Here is what it should contain and how to build...
- Principal Contractor Checklist: The First Week on SiteThe first week on site sets the standard for the whole construction phase. This checklist covers what a Principal...
Free templates
Need support with cdm advisory on your project?