Retention is a percentage held back from each interim payment as security against defects. It is usually released in two stages: part at practical completion and the rest at the end of the defects or rectification period. For many contractors and subcontractors it is a significant amount of money that is easy to lose track of.
Typical retention terms
- Rate: commonly three to five percent of each interim payment
- Limit: some contracts cap total retention at a fixed sum or percentage of the contract value
- First release: often half at practical completion
- Second release: the remainder at the end of the defects period, commonly twelve months later
The contract always governs. Check the contract particulars or subcontract order for the actual figures.
Retention down the supply chain
Subcontractors often find their retention release linked to the main contract or to completion of the whole project rather than their own package. That can mean waiting long after their work is finished. Read the release terms carefully before signing.
Retention under JCT and NEC
JCT contracts include retention provisions and set out how retention is held. NEC4 deals with retention through a secondary option, so it only applies where that option is chosen.
How to recover retention on time
- 1Record every release date at the start of the project
- 2Track practical completion and the end of defects for every contract and subcontract
- 3Close out defects promptly with evidence
- 4Agree the final account so there is no reason to hold money back
- 5Apply for release in writing when it falls due
Retention and payment notices
Retention release should appear in the relevant application and payment notice. If it is withheld without a valid Pay Less notice, the Construction Act payment rules apply. See payment and Pay Less notices.
Help with retention and accounts
Matthews & Roberts provides quantity surveying for subcontractors and contractors in Salford, the Wirral, Liverpool and across the North West.
Frequently asked questions
What is retention in construction?
Retention is a percentage of each interim payment held back by the payer as security against defects. It is released in stages once the work is complete and defects are put right.
What is the usual retention percentage?
Retention is commonly between three and five percent, but the contract sets the actual figure and any limit.
When is retention released?
Typically half is released at practical completion and the remainder at the end of the defects or rectification period, though subcontracts sometimes link release to the main contract.
Commercial control
Related guides and templates
A commercial review draws on more than one record. These guides and templates support it.
Guides
- Cost Value Reconciliation in Construction: A Contractor's Guide to CVRHow to compare cost with value and report the margin honestly.
- What Does a Construction Commercial Manager Do?Where commercial management adds margin on a project.
- Quantity Surveyor vs Commercial Manager: What Is the Difference?Which commercial role fits the job in front of you.
- What Does a Quantity Surveyor Do for a Contractor?What a contractor QS covers from tender to final account.
Free templates
Need support with quantity surveying on your project?