Infrastructure Sector

Building the
Foundations

Programme Management | NEC Administration | CDM Compliance

Major infrastructure demands rigorous governance, specialist procurement knowledge, and construction-phase management that anticipates the unique risks of civil engineering. Matthews & Roberts provides the programme management and CDM compliance that keeps infrastructure programmes on track — from £500k schemes to £500M+ portfolios.

The Challenge

Where programme complexity meets construction risk

Infrastructure projects operate at the intersection of multiple technical disciplines, regulatory regimes, and stakeholder interests. Ground conditions are uncertain, statutory consents are complex, environmental obligations are stringent, and the consequences of programme failure are measured in millions. Effective infrastructure delivery requires project management teams who understand civil engineering risk, procurement strategy, and the contractual frameworks — particularly NEC — that govern the sector.

£600B+

UK National Infrastructure Pipeline

NEC4

Dominant contract form

75%

Cost overrun on major projects (avg)

CDM

High-risk sector classification

Procurement Strategy

Choosing the right procurement route

The procurement route determines risk allocation, programme, cost certainty, and quality outcomes. Select a route to explore its characteristics.

Traditional (Design-Bid-Build)

Full design completed before contractor appointment. Client retains design control through separate design team. Competitive tendering on complete information delivers price certainty.

Advantages

Price certainty from complete design
Full client design control
Competitive tendering on like-for-like basis
Clear separation of design and construction liability

Considerations

Longer overall programme
Change management more complex post-contract
Contractor buildability input limited
Design team coordination remains with client

Best for: Heritage infrastructure, water treatment upgrades, bridge refurbishments where design certainty is critical

Risk profile: Design risk retained by client. Construction risk transferred to contractor on fixed-price basis.

Project Lifecycle

Infrastructure delivery phases

Feasibility & Optioneering

Defining the need, assessing options, and establishing the business case for infrastructure investment. Includes environmental constraints mapping, land referencing, and preliminary cost planning.

Key Deliverables

Options appraisal report
Outline business case
Environmental constraints mapping
Preliminary cost estimate
Stakeholder engagement strategy
Outline programme
What We Deliver

Infrastructure delivery services

Programme Management

Strategic programme leadership across multi-project infrastructure portfolios including AMP, CP, and capital investment programmes.

Programme governancePortfolio reportingBenefits realisationResource planning

Project Management

Client-side project delivery from feasibility through construction to handover for individual infrastructure schemes.

Project controlsProgress monitoringStakeholder managementHandover governance

CDM Advisory & Principal Designer

CDM 2015 compliance for infrastructure projects including confined spaces, working near live services, and complex temporary works.

Pre-construction infoH&S FileDesign risk managementPD appointment

Contract Administration

NEC3/NEC4 and JCT contract administration including payment certification, compensation events, and dispute avoidance.

Payment certificationCE assessmentContract complianceDispute avoidance

Quantity Surveying

Cost management for infrastructure including target cost management, bill of quantities, and final account negotiation.

Cost planningTarget cost monitoringValuationFinal accounts

Quality Assurance

Quality management systems ensuring infrastructure meets specification requirements, statutory standards, and adoption criteria.

ITP developmentHold point managementNCR trackingAdoption compliance
Risk Management

Infrastructure risk register

Unforeseen ground conditions

Critical

Impact

Foundation redesign, programme delay, cost escalation

Mitigation

Phased ground investigation with contingency in GI specification

Contaminated land discovery

High

Impact

Remediation costs, environmental permits, disposal levies

Mitigation

Phase I/II desk study and intrusive investigation pre-tender

Flood risk during construction

High

Impact

Work stoppage, temporary works failure, environmental incident

Mitigation

Flood risk assessment, temporary flood defences, seasonal programming

Protected species encountered

High

Impact

Seasonal working restrictions, mitigation licences, programme delay

Mitigation

Preliminary Ecological Appraisal and species surveys during feasibility

Client Success

Infrastructure projects delivered

Matthews & Roberts managed a complex multi-utility infrastructure programme across five development phases. Their NEC contract administration and programme coordination kept all packages aligned despite challenging ground conditions and statutory diversions.

Programme Director

Infrastructure Developer, Manchester

£42M programme delivered — 3 weeks ahead of schedule

Our flood defence upgrade required working within a live operational environment with significant CDM challenges. Matthews & Roberts provided both Principal Designer services and construction phase management that kept the project safe and compliant throughout.

Capital Delivery Manager

Water Utility, Yorkshire

Zero reportable incidents across 14-month construction
FAQ

Infrastructure project questions

We provide project and programme management across the full spectrum of civil infrastructure — flood defences, water and wastewater treatment, pumping stations, highways and bridges, energy infrastructure, drainage and attenuation, and utility networks. Our experience spans both greenfield construction and refurbishment of existing operational assets.

Yes. We provide full NEC3 and NEC4 contract administration including project manager and supervisor roles. This covers payment certification, compensation event assessment, programme management under clause 31-32, early warning procedures, and dispute avoidance. We also administer JCT and bespoke infrastructure contracts.

Infrastructure projects carry specific CDM risks including working near live services, confined space entry, deep excavations, working over or near water, temporary works in unstable ground, and public interface management. Our Principal Designers develop pre-construction information addressing these sector-specific hazards and ensure designers eliminate or reduce risks through design decisions.

Yes. We have experience supporting water company AMP (Asset Management Period) programmes and Network Rail Control Period frameworks. This includes programme-level governance, portfolio prioritisation, contractor framework management, and regulatory reporting against OFWAT or ORR requirements.

The optimal procurement route depends on project complexity, risk profile, and client capability. We advise on traditional, design and build, ECI (early contractor involvement), target cost, and alliance/framework approaches. For complex infrastructure, ECI under NEC often provides the best balance of contractor input and client control.

Yes. Infrastructure projects frequently involve multiple statutory consultees, landowners, local authorities, and community stakeholders. We develop and implement stakeholder engagement strategies, manage consultation processes, and coordinate with bodies including the Environment Agency, Natural England, Historic England, and statutory undertakers.

Infrastructure construction frequently involves significant temporary works — cofferdams, sheet piling, temporary bridges, dewatering systems, and ground support. We provide temporary works coordination, design review, and inspection regimes in accordance with BS 5975 and the Temporary Works Forum guidance.

We coordinate environmental compliance across planning conditions, Environmental Impact Assessment commitments, environmental permits, and Construction Environmental Management Plans. This includes pollution prevention, waste management, ecological mitigation, noise and vibration monitoring, and water quality protection throughout construction.

Get Started

Delivering infrastructure?

From flood defences to energy infrastructure, we provide the programme management, CDM advisory, and contract administration that keeps major infrastructure on track.

Programme and project management for infrastructure portfolios
NEC3/NEC4 contract administration and supervisor services
CDM Principal Designer for high-risk civil engineering
Procurement strategy and contractor evaluation
Quality assurance and commissioning management
Projects from £500k to £500M+

Get in Touch

We will aim to respond within 24hrs.

Client Portal

The Client Portal provides secure access to project documents, progress updates, and direct communication with your Matthews & Roberts team.

Request access: info@matthewsroberts.com

Portal access is provided to approved clients. Contact us if you need support.

Existing client?

Access your project portal to view documents and track progress.

New enquiry?

Tell us about your project and we'll respond within 24 hours.